Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0824-01700
Permit Details
Apply Date:
08/30/2024
Applicant:
Arturo Zatarain
Description:
SUNNY DAYS - Tenant improvement to an existing masonry commercial building. The building is to remain as it is with no additional square footage added. The use will be retail.
Permit Reviews
Permit Number - TC-COM-0824-01700
Permit Status: Complete
Permit Description: SUNNY DAYS - Tenant improvement to an existing masonry commercial building. The building is to remain as it is with no additional square footage added. The use will be retail.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/31/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/03/2025 | APPROVED |
09/09/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 09/20/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0824-01700
Permit Status: Complete
Permit Description: SUNNY DAYS - Tenant improvement to an existing masonry commercial building. The building is to remain as it is with no additional square footage added. The use will be retail.
Date | Description | Comments |
---|---|---|
09/09/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
10/09/2024 | Sewer/Wastewater |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0824-01700
Permite Description: SUNNY DAYS - Tenant improvement to an existing masonry commercial building. The building is to remain as it is with no additional square footage added. The use will be retail.
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/04/2024 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | Underground plumbing in interior of suite. Ok to cover progress areas. |
01/24/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0824-01700
Permit Description: SUNNY DAYS - Tenant improvement to an existing masonry commercial building. The building is to remain as it is with no additional square footage added. The use will be retail.
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/23/2024 | COT - HCEL - Electrical Intermediate | Passed | 12-23-24, electrical intermediate inspection approved. Okay to continue with construction. | |
01/03/2025 | COT - LCPL - Plumbing Intermediate | Passed | 1-3-25, plumbing intermediate approved. Okay to continue with construction. | |
01/03/2025 | COT - HCME - Mechanical Intermediate | Passed | 1-3-25, mechanical intermediate approved. Okay to continue with construction. | |
01/22/2025 | COT - HCBU - Building Above Ceiling | Passed | ||
01/22/2025 | COT - HCBU - Building Progress | Passed | ||
01/22/2025 | COT - HCEL - Electrical Above Ceiling | Passed | ||
01/22/2025 | COT - HCEL - Electrical Progress | Passed | ||
01/22/2025 | COT - HCME - Mechanical Above Ceiling | Passed | ||
01/22/2025 | COT - HCME - Mechanical Progress | Passed | ||
01/22/2025 | COT - LCPL - Plumbing Final | Passed | ||
01/22/2025 | COT - HCME - Mechanical Final | Passed | ||
01/24/2025 | BULD - Electrical Clearance | Passed | No clearance required. | |
01/24/2025 | COT - FCON - Fire - Final | Passed | ||
01/24/2025 | COT - LCEL - Electrical Final | Passed | ||
01/24/2025 | COT - LCME - Mechanical Final | Passed | ||
01/24/2025 | ENGR Engineering Final | Passed | ||
01/24/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
01/24/2025 | COT - HCBU - Building Final | Passed | ||
01/24/2025 | COT - LCBU - Building Final | Passed | ||
01/27/2025 | COT - HCEL - Electrical Final | Passed | ||
01/27/2025 | COT - HCBU - CofO | Passed | Ok to make application for Certificate of Occupancy. |