Permit: TC-COM-0824-01597
Permit Details
Status:
Inspections Complete
Type:
Commercial Building
Address:
440 N GRANDE AV BLDG 3
Address NEW:
440 N GRANDE AV BLDG 3
Apply Date:
08/14/2024
Applicant:
Adrian Zubiran
Description:
BUILDING 3 NORTH PV SYSTEM (POI 3), MASTER PLANSET IS UNDER TC-COM-0624-01142
Permit Reviews
Permit Number - TC-COM-0824-01597
Permit Status: Inspections complete
Permit Description: BUILDING 3 NORTH PV SYSTEM (POI 3), MASTER PLANSET IS UNDER TC-COM-0624-01142
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/25/2024 | COMMERCIAL REVIEW - FULL v.3 | 09/25/2024 | APPROVED |
| 08/22/2024 | COMMERCIAL REVIEW - FULL v.2 | 09/23/2024 | REQUIRES RESUBMIT |
| 09/25/2024 | RESTAMP - COMMERCIAL v.1 | 09/26/2024 | APPROVED |
| 08/16/2024 | COMMERCIAL REVIEW - FULL v.1 | 08/16/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0824-01597
Permit Status: Inspections complete
Permit Description: BUILDING 3 NORTH PV SYSTEM (POI 3), MASTER PLANSET IS UNDER TC-COM-0624-01142
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 09/19/2024 | SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION IS REQUIRED. |
| 09/19/2024 | SPECIAL INSPECTION OF FABRICATORS IS REQUIRED. |
| 09/19/2024 | SPECIAL INSPECTION FOR SOILS IS REQUIRED. |
| 09/19/2024 | SPECIAL INSPECTION FOR STRUCTURAL STEEL IS REQUIRED. |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: TC-COM-0824-01597
Permite Description: BUILDING 3 NORTH PV SYSTEM (POI 3), MASTER PLANSET IS UNDER TC-COM-0624-01142
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/07/2024 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Rebar on steel columns for building #3. Ok to place,concrete in progress areas. |
| 10/07/2024 | COT - CSOL - Grounding/Bonding Solar Project | N/A | Partial Pass | Eufer on steel,columns for building #3. |
| 12/31/2024 | BULD - Electrical Clearance | N/A | Partial Pass | Verbal clearance to TEP INCR. BUILDING #3 (NORTH). 12/31/2024 |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: TC-COM-0824-01597
Permit Description: BUILDING 3 NORTH PV SYSTEM (POI 3), MASTER PLANSET IS UNDER TC-COM-0624-01142
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/21/2025 | COT - CSOL - Electrical Final Solar Project | Passed | ||
| 01/21/2025 | COT - FCON - Fire - Final | Passed | ||
| 01/21/2025 | COT - LCBU - Building Final | Passed | ||
| 01/21/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 01/21/2025 | COT - LCEL - Electrical Final | Passed | ||
| 01/21/2025 | ENGR Engineering Final | Passed | ||
| 01/21/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 01/21/2025 | COT - CSOL - Electrical Intermediate Solar Project | Passed | ||
| 01/21/2025 | COT - CSOL - Electrical Progress Solar Project | Passed | ||
| 01/21/2025 | COT - CSOL - Electrical Underground Solar Project | Passed | ||
| 01/21/2025 | COT - CSOL - Outdoor Lighting Solar Project | Passed | ||
| 01/21/2025 | COT - CSOL - Grounding/Bonding Solar Project | Passed | ||
| 01/21/2025 | COT - LCBU - Framing | Passed | ||
| 01/21/2025 | BULD - Electrical Clearance | Passed | Approved building 3 (north) - DGC Clearance to TEP is required for the solar meter (#159900281) |