Permit Details

Status:
Inspections
Type:
Commercial Building
Apply Date:
08/14/2024
Applicant:
Austin Matson
Description:
BUILDING 2 PV SOLAR SYSTEM (MASTER PLAN SET UNDER TC-COM-0624-01142)

Permit Reviews

Permit Number - TC-COM-0824-01596
Permit Status: Inspections
Permit Description: BUILDING 2 PV SOLAR SYSTEM (MASTER PLAN SET UNDER TC-COM-0624-01142)
Start Date Submittal Complete Date Status  
09/26/2024 RESTAMP - COMMERCIAL v.1 09/26/2024 APPROVED Review Details
08/16/2024 COMMERCIAL REVIEW - FULL v.1 08/16/2024 REQUIRES RESUBMIT Review Details
08/22/2024 COMMERCIAL REVIEW - FULL v.2 09/23/2024 REQUIRES RESUBMIT Review Details
09/25/2024 COMMERCIAL REVIEW - FULL v.3 09/26/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0824-01596
Permit Status: Inspections
Permit Description: BUILDING 2 PV SOLAR SYSTEM (MASTER PLAN SET UNDER TC-COM-0624-01142)
Total Outstanding Activity Conditions - 4
Date Name
09/26/2024 SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION IS REQUIRED.
09/26/2024 SPECIAL INSPECTION FOR FABRICATORS IS REQUIRED.
09/26/2024 SPECIAL INSPECTION FOR SOILS IS REQUIRED.
09/26/2024 SPECIAL INSPECTION FOR STRUCTURAL IS REQUIRED.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-COM-0824-01596
Permite Description: BUILDING 2 PV SOLAR SYSTEM (MASTER PLAN SET UNDER TC-COM-0624-01142)
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
10/07/2024 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass Rebar on steel caisson,columns for,building #2. Ok to,place concrete in progress areas.
10/07/2024 COT - CSOL - Grounding/Bonding Solar Project N/A Partial Pass Euler in column caisson footings for,building #2

Completed Inspections

Permit Status: Inspections
Permit Number: TC-COM-0824-01596
Permit Description: BUILDING 2 PV SOLAR SYSTEM (MASTER PLAN SET UNDER TC-COM-0624-01142)
Total Completed Inspections - 1
Date Description Inspector Results Comments
10/11/2024 COT - CSOL - Electrical Underground Solar Project Passed Approved underground electrical conduit from service panel equipment at Building 1 to the solar equipment at PV structure 1 and continued to PV structure 2 and Building 2. Underground electrical conduit also approved from PV structure 3 to service panel equipment at Building 3.
All underground is completer, okay to backfill and for concrete/pavement placement