Public Storage #07112 86-9 KWDC Roof Top Solar/PV System

Permit Reviews

Permit Number - TC-COM-0824-01509
Permit Status: Inspections complete
Permit Description: Public Storage #07112 86-9 KWDC Roof Top Solar/PV System
Start Date Submittal Complete Date Status  
08/05/2024 COMMERCIAL REVIEW - FULL v.1 09/05/2024 REQUIRES RESUBMIT Review Details
01/21/2025 COMMERCIAL REVIEW - FULL v.3 02/06/2025 REQUIRES RESUBMIT Review Details
02/26/2025 COMMERCIAL REVIEW - FULL v.4 03/17/2025 APPROVED Review Details
03/17/2025 RESTAMP - COMMERCIAL v.1 03/27/2025 APPROVED Review Details
09/10/2024 COMMERCIAL REVIEW - FULL v.2 10/09/2024 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-0824-01509
Permit Status: Inspections complete
Permit Description: Public Storage #07112 86-9 KWDC Roof Top Solar/PV System
Date Description Comments
03/27/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-0824-01509
Permite Description: Public Storage #07112 86-9 KWDC Roof Top Solar/PV System
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
COT - FCON - Fire - Final N/A Not Ready

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-0824-01509
Permit Description: Public Storage #07112 86-9 KWDC Roof Top Solar/PV System
Total Completed Inspections - 9
Date Description Inspector Results Comments
04/09/2025 COT - CSOL - Electrical Underground Solar Project Passed Approved electrical underground conduits from building A to the south side wall SES location, okay to backfill and concrete placement of progress areas
04/30/2025 BULD - Electrical Clearance Passed 4-30-25, PV System verified per plans-DGC/DGL clearance issued to TEP.
04/30/2025 COT - LCBU - Building Final Passed 4-30-25, building & electrical final for PV System approved.
04/30/2025 COT - CSOL - Electrical Final Solar Project Passed 4-30-25, electrical final for PV System approved.
04/30/2025 COT - CSOL - Electrical Progress Solar Project Passed 4-30-25, building & electrical final for PV System approved.
04/30/2025 COT - CSOL - Grounding/Bonding Solar Project Passed
05/07/2025 ENGR Engineering Final Passed
05/06/2025 TRSP - ROW - Final/Close-Out Passed
11/24/2025 COT - FCON - Fire - Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-PS_07112_PERMIT-COMBINED SET_EE STAMPED_V3.PDF DOCUMENTS VIEW
7825 E SPEEDWAY TUSCON AZ - STRUCTURAL REPORT - REV 0_V2.PDF DOCUMENTS VIEW
PUBLIC STORAGE 27102 TUCSON AZ NXT_FULL CALCULATION REPORT_V2.PDF DOCUMENTS VIEW