Permit: TC-COM-0823-01971
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
5151 E SPEEDWAY BL
Address NEW:
5151 E SPEEDWAY BL
Apply Date:
08/14/2023
Applicant:
Jaris Brenneman
Description:
Coffee Wow Phase 1: Equipment and millwork modifications to existing coffee bar and lid bar.
Permit Reviews
Permit Number - TC-COM-0823-01971
Permit Status: Complete
Permit Description: Coffee Wow Phase 1: Equipment and millwork modifications to existing coffee bar and lid bar.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/09/2023 | RESTAMP - COMMERCIAL v.1 | 10/11/2023 | APPROVED |
| 08/14/2023 | COMMERCIAL REVIEW - FULL v.1 | 09/18/2023 | REQUIRES RESUBMIT |
| 10/03/2023 | COMMERCIAL REVIEW - FULL v.2 | 10/09/2023 | APPROVED |
| 03/16/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/21/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0823-01971
Permit Status: Complete
Permit Description: Coffee Wow Phase 1: Equipment and millwork modifications to existing coffee bar and lid bar.
| Date | Description | Comments |
|---|---|---|
| 09/18/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 09/18/2023 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0823-01971
Permite Description: Coffee Wow Phase 1: Equipment and millwork modifications to existing coffee bar and lid bar.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/13/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0823-01971
Permit Description: Coffee Wow Phase 1: Equipment and millwork modifications to existing coffee bar and lid bar.
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/13/2023 | COT - LCBU - Building Final | Passed | 10/13/23: final approved. | |
| 10/13/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 10/13/2023 | COT - LCME - Mechanical Final | Passed | ||
| 10/13/2023 | COT - LCEL - Electrical Final | Passed | ||
| 10/13/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 10/13/2023 | BULD - Electrical Clearance | Passed | ||
| 10/13/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 10/13/2023 | COT - FCON - Fire - Final | Passed |