Permit Details

Status:
Revision Fees Due
Type:
Commercial Building
Address NEW:
3105 N CAMPBELL AV
Apply Date:
07/02/2025
Applicant:
Description:
NEW SHELL CONSTRUCTION, INCLUDING THE INSTALLATION OF REQUIRED UTILITY FIXTURES AND ROUGH-INS TO SUPPORT FUTURE TENANT IMPROVEMENTS. ADDITIONALLY, A NEW PARKING LOT WILL BE CONSTRUCTED, PROVIDING ACCESS FROM BOTH CAMPBELL AVENUE AND HEDRICK DRIVE TO ACCOMMODATE THE DEVELOPMENT ’S COMMERCIAL TENANTS.

Permit Reviews

Permit Number - TC-COM-0725-01290
Permit Status: Revision fees due
Permit Description: NEW SHELL CONSTRUCTION, INCLUDING THE INSTALLATION OF REQUIRED UTILITY FIXTURES AND ROUGH-INS TO SUPPORT FUTURE TENANT IMPROVEMENTS. ADDITIONALLY, A NEW PARKING LOT WILL BE CONSTRUCTED, PROVIDING ACCESS FROM BOTH CAMPBELL AVENUE AND HEDRICK DRIVE TO ACCOMMODATE THE DEVELOPMENT ’S COMMERCIAL TENANTS.
Start Date Submittal Complete Date Status  
09/05/2025 ADMINISTRATIVE v.1 09/05/2025 REQUIRES RESUBMIT Review Details
07/10/2025 COMMERCIAL REVIEW - FULL v.1 08/04/2025 REQUIRES RESUBMIT Review Details
08/08/2025 COMMERCIAL REVIEW - FULL v.2 08/29/2025 REQUIRES RESUBMIT Review Details
04/02/2026 SPECIAL INSPECTION REVIEW v.3 04/08/2026 APPROVED Review Details
09/26/2025 ADMINISTRATIVE v.2 09/26/2025 APPROVED Review Details
09/02/2025 RESTAMP - COMMERCIAL v.1 09/05/2025 APPROVED Review Details
03/19/2026 SPECIAL INSPECTION REVIEW v.1 03/19/2026 REQUIRES RESUBMIT Review Details
06/18/2026 COMMERCIAL REVIEW - FULL REVISION v.1 07/14/2026 APPROVED Review Details
09/02/2025 COMMERCIAL REVIEW - FULL v.3 09/02/2025 APPROVED Review Details
03/25/2026 SPECIAL INSPECTION REVIEW v.2 03/26/2026 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-0725-01290
Permit Status: Revision fees due
Permit Description: NEW SHELL CONSTRUCTION, INCLUDING THE INSTALLATION OF REQUIRED UTILITY FIXTURES AND ROUGH-INS TO SUPPORT FUTURE TENANT IMPROVEMENTS. ADDITIONALLY, A NEW PARKING LOT WILL BE CONSTRUCTED, PROVIDING ACCESS FROM BOTH CAMPBELL AVENUE AND HEDRICK DRIVE TO ACCOMMODATE THE DEVELOPMENT ’S COMMERCIAL TENANTS.
Date Description Comments
08/12/2025 AIR BALANCING REPORT IS REQUIRED.
08/12/2025 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
08/12/2025 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
08/12/2025 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
08/12/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
07/28/2025 An intermediate Elevation Certificate is required PRIOR TO GRADING and/or PRE-SLAB INSPECTION. Submit under TE-FPU-0225-00052
08/12/2025 Masonry Inspection Report submittal review is required.
08/12/2025 Post-Installed Anchor Inspection Report is required.
08/12/2025 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
07/28/2025 Submission of the final Elevation Certificate and completion of the Floodplain Use Permit under TE-FPU-0225-00052 is required PRIOR TO FINALING this permit.
07/10/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
08/12/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
08/12/2025 WATER STERILIZATION REPORT IS REQUIRED.
08/12/2025 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Revision Fees Due
Permit Number: TC-COM-0725-01290
Permite Description: NEW SHELL CONSTRUCTION, INCLUDING THE INSTALLATION OF REQUIRED UTILITY FIXTURES AND ROUGH-INS TO SUPPORT FUTURE TENANT IMPROVEMENTS. ADDITIONALLY, A NEW PARKING LOT WILL BE CONSTRUCTED, PROVIDING ACCESS FROM BOTH CAMPBELL AVENUE AND HEDRICK DRIVE TO ACCOMMODATE THE DEVELOPMENT ’S COMMERCIAL TENANTS.
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
11/26/2025 COT - HCBU - Building Progress N/A Canceled Canceled inspection. 11/26/2025
11/04/2025 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass
03/20/2026 COT - BULD - SWG Clearance N/A Not Applicable
03/20/2026 COT - HCPL - Gas Final N/A Not Applicable
01/09/2026 COT - HCPL - Plumbing Progress N/A Partial Pass 12/24/25 waterline from four backflow preventers to building OK to cover
1/8/26 lines, 2 grease and one sewer on east side all ok to cover grease separator not complete on leak check
1/9/26: Grease tank leak check passed inspection
11/13/2025 COT - HCBU - Framing N/A Partial Pass
03/20/2026 COT - FCON - Fire - Final N/A Partial Pass Address shall be added to the building.
10/21/2025 COT - HCBU - Masonry Pregrout N/A Partial Pass CMU walls at Northeast portion of structure at 8’ - 16’ with clean out portals at 8’. Ok to place concrete in progress areas.
03/19/2026 COT - HCBU - Building Final N/A Not Ready

Completed Inspections

Permit Status: Revision Fees Due
Permit Number: TC-COM-0725-01290
Permit Description: NEW SHELL CONSTRUCTION, INCLUDING THE INSTALLATION OF REQUIRED UTILITY FIXTURES AND ROUGH-INS TO SUPPORT FUTURE TENANT IMPROVEMENTS. ADDITIONALLY, A NEW PARKING LOT WILL BE CONSTRUCTED, PROVIDING ACCESS FROM BOTH CAMPBELL AVENUE AND HEDRICK DRIVE TO ACCOMMODATE THE DEVELOPMENT ’S COMMERCIAL TENANTS.
Total Completed Inspections - 32
Date Description Inspector Results Comments
11/04/2025 COT - HCBU - Roof Nailing Passed
12/04/2025 COT - HCBU - Exterior Clips/Sheathing Passed
12/19/2025 COT - HCPL - Sewer Passed
01/05/2026 COT - HCEL - Electrical Underground Passed
01/20/2026 BULD - Electrical Clearance Passed for 3105 N CAMPBELL. HP only
01/30/2026 COT - HCEL - Electrical Progress Passed
02/05/2026 COT - HCBU - Building Progress Passed
02/12/2026 COT - HCPL - Plumbing Roof Drains Passed
02/12/2026 COT - HCPL - Plumbing Final Passed
02/27/2026 COT - HCBU - Excavation/Rebar/Zoning Passed
03/03/2026 COT - HCBU - Stem Wall/Retaining Wall Passed
03/04/2026 COT - HCBU - Preslab Passed
03/20/2026 COT - HCPL - Gas Pressure Test Passed
03/20/2026 TRSP - ROW - Final/Close-Out Passed all work has been completed in the right away
03/20/2026 COT - FCON - Alarm - Final Passed Approved on 3/18/26 on permit TF-FCP-1125-00998
03/20/2026 COT - HCEL - Outdoor Lighting Passed
03/20/2026 COT - HCME - Mechanical Progress Passed
03/20/2026 COT - HCPL - Backwater Valve Passed
03/20/2026 ENGR Engineering Final Passed Shell building and necessary site work is complete, not okay for public access until TI work is complete.
03/20/2026 COT - FCON - Sprinkler - Final Passed Approved on 3/19/26 on permit TF-FCP-1025-00908
03/20/2026 COT - HCME - Mechanical Final Passed
03/20/2026 COT - HCBU - Sustainability Passed
03/20/2026 COT - HCBU - Interior Shear Bracing Passed
03/20/2026 COT - HCEL - Electrical Above Ceiling Passed
03/20/2026 COT - HCEL - Electrical Final Passed
03/20/2026 PDSD Heavy Commercial Building Division Pre-Construction Meeting Passed
03/20/2026 COT - HCPL - Plumbing Progress Passed
03/20/2026 COT - HCEL - Grounding/Bonding Passed
03/20/2026 COT - HCPL - Yard Water Line Passed
03/20/2026 COT - HCBU - Framing Passed
03/26/2026 COT - FCON - Fire - Final Passed
04/10/2026 COT - HCBU - Building Final Passed