Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
07/29/2024
Applicant:
Ed Turpin
Description:
4800 SF Addition to the Fleet Building

Permit Reviews

Permit Number - TC-COM-0724-01450
Permit Status: Issued
Permit Description: 4800 SF Addition to the Fleet Building
Start Date Submittal Complete Date Status  
10/07/2024 COMMERCIAL REVIEW - LIMITED v.2 10/22/2024 REQUIRES RESUBMIT Review Details
12/02/2024 RESTAMP - COMMERCIAL v.1 12/03/2024 APPROVED Review Details
03/03/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/07/2025 APPROVED Review Details
11/05/2024 COMMERCIAL REVIEW - LIMITED v.3 12/02/2024 APPROVED Review Details
01/27/2026 COMMERCIAL REVIEW - FULL REVISION v.1 01/30/2026 APPROVED Review Details
12/08/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/10/2025 REQUIRES RESUBMIT Review Details
04/23/2025 COMMERCIAL REVIEW - FULL REVISION v.1 05/12/2025 APPROVED Review Details
07/30/2024 COMMERCIAL REVIEW - LIMITED v.1 08/15/2024 REQUIRES RESUBMIT Review Details
12/23/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 12/29/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0724-01450
Permit Status: Issued
Permit Description: 4800 SF Addition to the Fleet Building
Total Outstanding Activity Conditions - 1
Date Name
08/15/2024 SPECIAL INSPECTION FOR STRUCTURAL STEEL IS REQUIRED.

Conditions

Permit Number - TC-COM-0724-01450
Permit Status: Issued
Permit Description: 4800 SF Addition to the Fleet Building
Date Description Comments
08/14/2024 AIR BALANCING REPORT FOR EF-1 IS REQUIRED.
08/15/2024 SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION INSTALLATION IS REQUIRED.
12/08/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
03/07/2025 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
08/15/2024 Pre-Engineered Metal Building Plans and Calculations must be submitted and approved prior to Final Inspection
08/15/2024 SPECIAL INSPECTION FOR POST-INSTALLED ANCHORS IS REQUIRED.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0724-01450
Permite Description: 4800 SF Addition to the Fleet Building
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
06/23/2025 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass Partial pass. Pad for fleet expansion approved. Reinforcements and footers approved. Okay for concrete placement. Pending forms for house keeping pad. 6/23/2025
06/23/2025 COT - LCBU - Preslab N/A Partial Pass Partial pass. Pad for fleet expansion approved. Reinforcements and footers approved. Okay for concrete placement. Pending forms for house keeping pad. 6/23/2025
06/30/2025 COT - LCPL - Plumbing Intermediate N/A Partial Pass 4" vent stubbed up from slab for floor drain. 6/30/2024
11/21/2025 BULD - Electrical Clearance N/A Not Applicable 11-21-25: not applicable.
11/25/2025 COT - LCBU - Building Final N/A Partial Pass Partial pass. Pending all required documents prior to finals. 11/25/2025
11/25/2025 COT - LCME - Mechanical Final N/A Partial Pass Partial pass. Pending air balance report prior to final. 11/25/2025

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0724-01450
Permit Description: 4800 SF Addition to the Fleet Building
Total Completed Inspections - 22
Date Description Inspector Results Comments
06/30/2025 COT - LCBU - Excavation/Rebar/Zoning Passed House keeping pad approved. Ready for concrete placement. 6/30/2025
06/30/2025 COT - LCBU - Preslab Passed House keeping pad approved. Ready for concrete placement. 6/30/2025
08/27/2025 COT - LCPL - Plumbing Final Passed
08/27/2025 COT - LCPL - Plumbing Intermediate Passed
08/27/2025 COT - LCPL - Rough Soil Passed
08/27/2025 COT - LCBU - Framing Passed
10/29/2025 COT - LCPL - Sewer Passed 10-29-25: inspected at underground plumbing inspection.
10/29/2025 COT - LCEL - Electrical Underground Passed 10-29-25: approved.
11/12/2025 COT - LCPL - Gas Pressure Test Passed 11-12-25: gas pressure test approved.
11/21/2025 COT - FCON - Fire - Final Passed
11/21/2025 COT - FCON - Sprinkler - Final Passed
11/21/2025 COT - LCEL - Electrical Above Ceiling Passed 11-21-25: electrical above ceiling approved.
11/21/2025 COT - BULD - SWG Clearance Passed 11-21-25: okay to energize meter #210321 which is located just east of TEP's main entry. Southwest Gas Clearance issued.
11/21/2025 ENGR Engineering Final Passed
11/21/2025 COT - LCME - Mechanical Intermediate Passed 11-21-25: mechanical intermediates approved.
11/21/2025 COT - LCEL - Electrical Intermediate Passed 11-21-25: approved.
11/21/2025 COT - LCEL - Grounding/Bonding Passed 11-21-25: approved.
11/21/2025 COT - LCEL - Outdoor Lighting Passed 11-21-25: outdoor lighting approved.
11/21/2025 TRSP - ROW - Final/Close-Out Passed All work completed outside of the right of way
11/25/2025 COT - LCEL - Electrical Final Passed
12/08/2025 COT - LCBU - Building Final Passed
12/08/2025 COT - LCME - Mechanical Final Passed