Permit: TC-COM-0724-01450
Permit Details
Status:
Needs Resubmittal
Type:
Commercial Building
Address:
3950 E IRVINGTON RD BLDG 6
Address NEW:
3950 E IRVINGTON RD BLDG 6
Apply Date:
07/29/2024
Applicant:
Ed Turpin
Description:
4800 SF Addition to the Fleet Building
Permit Reviews
Permit Number - TC-COM-0724-01450
Permit Status: Needs resubmittal
Permit Description: 4800 SF Addition to the Fleet Building
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/07/2024 | COMMERCIAL REVIEW - LIMITED v.2 | 10/22/2024 | REQUIRES RESUBMIT |
| 12/02/2024 | RESTAMP - COMMERCIAL v.1 | 12/03/2024 | APPROVED |
| 03/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/07/2025 | APPROVED |
| 11/05/2024 | COMMERCIAL REVIEW - LIMITED v.3 | 12/02/2024 | APPROVED |
| 12/08/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/10/2025 | REQUIRES RESUBMIT |
| 04/23/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 05/12/2025 | APPROVED |
| 07/30/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 08/15/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0724-01450
Permit Status: Needs resubmittal
Permit Description: 4800 SF Addition to the Fleet Building
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 08/14/2024 | AIR BALANCING REPORT FOR EF-1 IS REQUIRED. |
| 08/15/2024 | SPECIAL INSPECTION FOR STRUCTURAL STEEL IS REQUIRED. |
Conditions
Permit Number - TC-COM-0724-01450
Permit Status: Needs resubmittal
Permit Description: 4800 SF Addition to the Fleet Building
| Date | Description | Comments |
|---|---|---|
| 08/15/2024 | SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION INSTALLATION IS REQUIRED. | |
| 12/08/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 03/07/2025 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 08/15/2024 | Pre-Engineered Metal Building Plans and Calculations must be submitted and approved prior to Final Inspection | |
| 08/15/2024 | SPECIAL INSPECTION FOR POST-INSTALLED ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0724-01450
Permite Description: 4800 SF Addition to the Fleet Building
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/23/2025 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Partial pass. Pad for fleet expansion approved. Reinforcements and footers approved. Okay for concrete placement. Pending forms for house keeping pad. 6/23/2025 |
| 06/23/2025 | COT - LCBU - Preslab | N/A | Partial Pass | Partial pass. Pad for fleet expansion approved. Reinforcements and footers approved. Okay for concrete placement. Pending forms for house keeping pad. 6/23/2025 |
| 06/30/2025 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | 4" vent stubbed up from slab for floor drain. 6/30/2024 |
| 11/21/2025 | BULD - Electrical Clearance | N/A | Not Applicable | 11-21-25: not applicable. |
| 11/25/2025 | COT - LCBU - Building Final | N/A | Partial Pass | Partial pass. Pending all required documents prior to finals. 11/25/2025 |
| 11/25/2025 | COT - LCME - Mechanical Final | N/A | Partial Pass | Partial pass. Pending air balance report prior to final. 11/25/2025 |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0724-01450
Permit Description: 4800 SF Addition to the Fleet Building
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/30/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | House keeping pad approved. Ready for concrete placement. 6/30/2025 | |
| 06/30/2025 | COT - LCBU - Preslab | Passed | House keeping pad approved. Ready for concrete placement. 6/30/2025 | |
| 08/27/2025 | COT - LCPL - Plumbing Final | Passed | ||
| 08/27/2025 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 08/27/2025 | COT - LCPL - Rough Soil | Passed | ||
| 08/27/2025 | COT - LCBU - Framing | Passed | ||
| 10/29/2025 | COT - LCPL - Sewer | Passed | 10-29-25: inspected at underground plumbing inspection. | |
| 10/29/2025 | COT - LCEL - Electrical Underground | Passed | 10-29-25: approved. | |
| 11/12/2025 | COT - LCPL - Gas Pressure Test | Passed | 11-12-25: gas pressure test approved. | |
| 11/21/2025 | COT - FCON - Fire - Final | Passed | ||
| 11/21/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 11/21/2025 | COT - LCEL - Electrical Above Ceiling | Passed | 11-21-25: electrical above ceiling approved. | |
| 11/21/2025 | COT - BULD - SWG Clearance | Passed | 11-21-25: okay to energize meter #210321 which is located just east of TEP's main entry. Southwest Gas Clearance issued. | |
| 11/21/2025 | ENGR Engineering Final | Passed | ||
| 11/21/2025 | COT - LCME - Mechanical Intermediate | Passed | 11-21-25: mechanical intermediates approved. | |
| 11/21/2025 | COT - LCEL - Electrical Intermediate | Passed | 11-21-25: approved. | |
| 11/21/2025 | COT - LCEL - Grounding/Bonding | Passed | 11-21-25: approved. | |
| 11/21/2025 | COT - LCEL - Outdoor Lighting | Passed | 11-21-25: outdoor lighting approved. | |
| 11/21/2025 | TRSP - ROW - Final/Close-Out | Passed | All work completed outside of the right of way | |
| 11/25/2025 | COT - LCEL - Electrical Final | Passed | ||
| 12/08/2025 | COT - LCBU - Building Final | Passed | ||
| 12/08/2025 | COT - LCME - Mechanical Final | Passed |