Permit: TC-COM-0724-01426
Permit Details
Apply Date:
07/25/2024
Applicant:
Andrew Venne
Description:
Adding new Hood for Fire house 13
Permit Reviews
Permit Number - TC-COM-0724-01426
Permit Status: Complete
Permit Description: Adding new Hood for Fire house 13
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/26/2024 | CIP - COMMERCIAL BUILDING - LIMITED REVIEW v.1 | 08/02/2024 | APPROVED |
| 07/25/2024 | COMMERCIAL REVIEW - LIMITED v.1 | 07/26/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0724-01426
Permite Description: Adding new Hood for Fire house 13
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/14/2025 | BULD - Electrical Clearance | N/A | Not Applicable | 3-14-25, not applicable |
| 03/14/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | 3-14-25, not applicable |
| 03/14/2025 | COT - LCME - Mechanical Final | N/A | Re-inspection required | 3-14-25, reinspect required-have electrician on site to remove dead front so that we may verify correct breakers for newly installed hood system (provide breakers' specifications'/listing),install new thermostat for hood system |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0724-01426
Permit Description: Adding new Hood for Fire house 13
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/14/2025 | COT - LCPL - Plumbing Final | Passed | 3-14-25, plumbing final approved. | |
| 03/17/2025 | COT - FCON - Fire - Final | Passed | ||
| 03/17/2025 | ENGR Engineering Final | Passed | ||
| 03/18/2025 | TRSP - ROW - Final/Close-Out | Passed | Work was completed on private property no impact to public right-of-way. | |
| 07/03/2025 | COT - LCBU - Building Final | Passed | ||
| 07/03/2025 | COT - LCEL - Electrical Final | Passed | ||
| 07/03/2025 | COT - LCME - Mechanical Final | Passed |