Permit: TC-COM-0724-01350
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
1601 W SAINT MARYS RD
Address NEW:
1601 W SAINT MARYS RD
Apply Date:
07/12/2024
Applicant:
Brandon Acosta
Description:
New Cath Lan in existing St Mary's Hospital
Permit Reviews
Permit Number - TC-COM-0724-01350
Permit Status: Complete
Permit Description: New Cath Lan in existing St Mary's Hospital
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/03/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 11/04/2025 | APPROVED |
| 03/10/2025 | COMMERCIAL REVIEW - FULL v.2 | 03/17/2025 | APPROVED |
| 11/08/2024 | RESTAMP - COMMERCIAL v.1 | 11/21/2024 | APPROVED |
| 03/17/2025 | RESTAMP - COMMERCIAL v.1 | 03/19/2025 | APPROVED |
| 02/01/2025 | COMMERCIAL REVIEW - FULL v.1 | 02/24/2025 | REQUIRES RESUBMIT |
| 07/12/2024 | COMMERCIAL REVIEW - FULL v.1 | 08/13/2024 | REQUIRES RESUBMIT |
| 12/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/17/2024 | APPROVED |
| 10/29/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/29/2025 | REQUIRES RESUBMIT |
| 11/05/2024 | COMMERCIAL REVIEW - FULL v.2 | 11/08/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0724-01350
Permit Status: Complete
Permit Description: New Cath Lan in existing St Mary's Hospital
| Date | Description | Comments |
|---|---|---|
| 11/08/2024 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. | |
| 11/08/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
| 07/12/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 11/08/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 11/08/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 11/08/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 12/17/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 12/12/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 11/08/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0724-01350
Permite Description: New Cath Lan in existing St Mary's Hospital
Total Outstanding Inspections - 13
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/23/2025 | COT - HCBU - Building Above Ceiling | N/A | Partial Pass | |
| 05/23/2025 | COT - HCBU - Framing | N/A | Partial Pass | 5/23/25 cath lab only for these results |
| 05/23/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | |
| 12/26/2024 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 12/26/24. Partial pass. Under ground plumbing for hand sink. |
| 04/15/2025 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | North west corner return hard duct. Main supply trunks x2 are in place. Okay to proceed progress areas. 4/15/2025 |
| 04/15/2025 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | Electrical in walls at north control room wall and south wall. 4/15/2025 |
| 08/15/2025 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 08/15/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 04/15/2025 | COT - HCBU - Building Progress | N/A | Partial Pass | |
| 08/15/2025 | COT - HCEL - Electrical Final | N/A | Partial Pass | Partial pass. Pending bathroom. 8/15/2025 |
| 08/15/2025 | COT - HCME - Mechanical Final | N/A | Partial Pass | Partial pass. Pending bathroom. Provide test and balance report prior to final. 8/15/2025 |
| 08/15/2025 | COT - HCPL - Medical Gas/Final | N/A | Partial Pass | Per previous notes. 8/15/2025 |
| 08/15/2025 | COT - HCPL - Plumbing Final | N/A | Partial Pass | Partial pass. Pending bathroom. 8/15/2025 |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0724-01350
Permit Description: New Cath Lan in existing St Mary's Hospital
Total Completed Inspections - 20
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/10/2025 | COT - HCPL - Medical Gas/Test | Passed | Med gas copper line pressure tested at 150psi. | |
| 07/02/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
| 07/16/2025 | COT - HCBU - Building Above Ceiling | Passed | Ok to cover ceiling. | |
| 07/16/2025 | COT - HCBU - Framing | Passed | OK to insulate and sheet rock | |
| 07/16/2025 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 07/25/2025 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 07/25/2025 | COT - HCME - Mechanical Intermediate | Passed | ||
| 07/25/2025 | COT - HCEL - Electrical Intermediate | Passed | ||
| 08/14/2025 | COT - FCON - Alarm - Final | Passed | ||
| 08/14/2025 | COT - FCON - Fire - Final | Passed | ||
| 08/15/2025 | ENGR Engineering Final | Passed | Cath lab finished- Access is provided for emergency exit to loading dock. Dumpster and port-a-john are staying in loading dock area for use because contractor has started w on another permit. tc-com-1024-02062 for CT scan. | |
| 08/15/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 08/14/2025 | COT - FCON - Sprinkler - Final | Passed | ||
| 08/15/2025 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 08/29/2025 | COT - HCBU - Building Progress | Passed | 8-29-25: approved. | |
| 08/29/2025 | COT - HCEL - Electrical Final | Passed | 8-29-25: approved. | |
| 08/29/2025 | COT - HCME - Mechanical Final | Passed | 8-29-25: mechanical final approved. | |
| 08/29/2025 | COT - HCPL - Medical Gas/Final | Passed | 8-29-25: med.gas final approved. | |
| 08/29/2025 | COT - HCPL - Plumbing Final | Passed | 8-29-25: plumbing final approved. | |
| 09/02/2025 | COT - HCBU - Building Final | Passed |