Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0724-01348
Permit Details
Apply Date:
07/11/2024
Applicant:
John Morgan
Description:
Update to Existing Customer Service Area
Permit Reviews
Permit Number - TC-COM-0724-01348
Permit Status: Inspections
Permit Description: Update to Existing Customer Service Area
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/29/2024 | RESTAMP - COMMERCIAL v.1 | 08/30/2024 | APPROVED |
07/12/2024 | COMMERCIAL REVIEW - FULL v.1 | 08/14/2024 | REQUIRES RESUBMIT |
08/28/2024 | COMMERCIAL REVIEW - FULL v.2 | 08/29/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0724-01348
Permit Status: Inspections
Permit Description: Update to Existing Customer Service Area
Date | Description | Comments |
---|---|---|
08/30/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0724-01348
Permite Description: Update to Existing Customer Service Area
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/31/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
11/18/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | Ok with temp Cof O level 4. just need an address on the street side of the building. |
11/18/2024 | ENGR Engineering Final | N/A | Not Applicable | No Exterior work, dumpster is being removed today. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-0724-01348
Permit Description: Update to Existing Customer Service Area
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/31/2024 | COT - LCPL - Rough Soil | Passed | 10/31/24: plumbing underground per plans ok to proceed | |
11/06/2024 | COT - LCBU - Framing | Passed | Metal stud rough framing is complete. Okay to install drywall. | |
11/06/2024 | COT - LCEL - Electrical Intermediate | Passed | Electrical rough-in is complete. Okay to install drywall. | |
11/18/2024 | BULD - Electrical Clearance | Passed | ||
11/18/2024 | COT - FCON - Sprinkler - Final | Passed | ||
11/18/2024 | COT - LCEL - Electrical Final | Passed | ||
11/18/2024 | COT - LCME - Mechanical Final | Passed | ||
11/18/2024 | COT - LCPL - Plumbing Final | Passed | ||
11/18/2024 | TRSP - ROW - Final/Close-Out | Passed | no impact to right of way on this work permit, traffic control on Valencia for separate job, rolloff still on site within private property | |
11/20/2024 | COT - LCBU - Building Final | Passed | 11-20-24, building final approved. | |
11/20/2024 | COT - LCEL - Electrical Above Ceiling | Passed | 11-20-24, electrical above ceiling per approved plans Final approved. | |
11/20/2024 | COT - LCME - Mechanical Intermediate | Passed | 11-20-24, mechanical,electrical above ceiling per approved plans Final approved. |