Permit: TC-COM-0723-01705
Permit Details
Apply Date:
07/13/2023
Applicant:
Michael Epstein
Description:
Tenant Improvement
Permit Reviews
Permit Number - TC-COM-0723-01705
Permit Status: Complete
Permit Description: Tenant Improvement
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/21/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/26/2024 | APPROVED |
04/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/04/2024 | APPROVED |
07/21/2023 | COMMERCIAL REVIEW - FULL v.2 | 09/26/2023 | APPROVED |
07/14/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/14/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0723-01705
Permit Status: Complete
Permit Description: Tenant Improvement
Date | Description | Comments |
---|---|---|
03/26/2024 | AIR BALANCING REPORT IS REQUIRED. | |
07/14/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
09/26/2023 | Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection. | |
09/26/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0723-01705
Permite Description: Tenant Improvement
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/20/2023 | COT - HCBU - Preslab | N/A | Partial Pass | 12/20/23: Preslab for plumbing underground passed. Ok to pour. |
02/29/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0723-01705
Permit Description: Tenant Improvement
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/15/2023 | COT - HCPL - Rough Soil | Passed | ||
01/11/2024 | COT - HCBU - Preslab | Passed | 12/20/23: Preslab for plumbing underground passed. Ok to pour. 1/11/24: ok to pour at conference room. |
|
01/11/2024 | COT - HCPL - Plumbing Intermediate | Passed | 1/11/24: plumbing intermediate in bathrooms 107,108,123 passed. | |
01/11/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
01/11/2024 | COT - HCEL - Electrical Underground | Passed | 1/11/24: 1/11/24: underground electrical for conference room per plan ok to pour. | |
01/16/2024 | COT - HCBU - Framing | Passed | ||
01/16/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
02/12/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
02/12/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
02/29/2024 | COT - HCBU - Building Above Ceiling | Passed | Ok to set ceiling tiles | |
02/29/2024 | COT - HCEL - Electrical Above Ceiling | Passed | Ok to set ceiling tiles. | |
02/29/2024 | BULD - Electrical Clearance | Passed | No electric clearance required, site is under power. | |
03/13/2024 | COT - FCON - Sprinkler - Final | Passed | ||
03/13/2024 | ENGR Engineering Final | Passed | ||
03/13/2024 | COT - HCPL - Plumbing Final | Passed | ||
03/13/2024 | COT - HCME - Mechanical Final | Passed | ||
03/13/2024 | COT - HCEL - Electrical Final | Passed | ||
03/13/2024 | COT - HCBU - Building Final | Passed | ||
03/13/2024 | COT - FCON - Fire - Final | Passed | ||
04/08/2024 | TRSP - ROW - Final/Close-Out | Passed | No issues in ROW. |