Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
07/07/2023
Applicant:
Samuel Lopez
Description:
Tenant improvement with no change of use. All site conditions to remain as is.

Permit Reviews

Permit Number - TC-COM-0723-01651
Permit Status: Complete
Permit Description: Tenant improvement with no change of use. All site conditions to remain as is.
Start Date Submittal Complete Date Status  
11/14/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/14/2023 APPROVED Review Details
07/07/2023 COMMERCIAL REVIEW - FULL v.1 08/04/2023 REQUIRES RESUBMIT Review Details
08/18/2023 COMMERCIAL REVIEW - FULL v.2 08/22/2023 APPROVED Review Details
08/22/2023 RESTAMP - COMMERCIAL v.1 08/24/2023 APPROVED Review Details
12/06/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/06/2023 REQUIRES RESUBMIT Review Details
12/07/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 12/07/2023 APPROVED Review Details

Conditions

Permit Number - TC-COM-0723-01651
Permit Status: Complete
Permit Description: Tenant improvement with no change of use. All site conditions to remain as is.
Date Description Comments
08/22/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
08/22/2023 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
08/22/2023 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
08/22/2023 WATER STERILIZATION REPORT IS REQUIRED.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0723-01651
Permit Description: Tenant improvement with no change of use. All site conditions to remain as is.
Total Completed Inspections - 9
Date Description Inspector Results Comments
11/17/2023 COT - FCON - Fire - Final Passed
11/17/2023 COT - FCON - Sprinkler - Final Passed passed by Will Motto
11/22/2023 BULD - Electrical Clearance Passed
11/22/2023 COT - BULD - SWG Clearance Passed
11/22/2023 ENGR Engineering Final Passed Sam Lopez
11/21/2023 TRSP - ROW - Final/Close-Out Passed
11/29/2023 COT - HCBU - Building Above Ceiling Passed
11/29/2023 COT - HCBU - Building Final Passed
11/29/2023 COT - HCBU - Building Progress Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
REV 23K0811_1 TURNER 12 05 2023 0748-2023-12-07_V2.PDF DOCUMENTS VIEW
AIE BALANCE AEGIS_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-PLAN_SET_2_V1.PDF DOCUMENTS VIEW
23065-AEGIS 1730 CAMBRIC-MECH COMCHECK_V1.PDF DOCUMENTS VIEW
23065-AEGIS 1730 CAMBRIC-MECH SIZING REPORT_V1.PDF DOCUMENTS VIEW
CONS-PLAN_SET1_V1.PDF DOCUMENTS VIEW