Permit: TC-COM-0626-00988
Permit Details
Status:
Needs Resubmittal
Type:
Commercial Building
Address:
1439 E HEDRICK DR
Address NEW:
1439 E HEDRICK DR
Apply Date:
06/29/2026
Applicant:
Ernesto Diaz Brown
Description:
New 18-unit apartment complex TC-COM-0626-00859 is the Master. This permit will cover Building C (Units 5-12).
Permit Reviews
Permit Number - TC-COM-0626-00988
Permit Status: Needs resubmittal
Permit Description: New 18-unit apartment complex
TC-COM-0626-00859 is the Master. This permit will cover Building C (Units 5-12).
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/01/2026 | COMMERCIAL REVIEW - FULL v.1 | 07/22/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0626-00988
Permit Status: Needs resubmittal
Permit Description: New 18-unit apartment complex
TC-COM-0626-00859 is the Master. This permit will cover Building C (Units 5-12).
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 07/01/2026 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
| 07/17/2026 | SPECIAL INSPECTION OF MASONRY CONSTRUCTION IS REQUIRED. |
| 07/17/2026 | SPECIAL INSPECTION OF POST-INSTALLED ANCHORS IS REQUIRED. |
| 07/17/2026 | SPECIAL INSPECTION OF SOILS IS REQUIRED. |
| 07/17/2026 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
| 07/17/2026 | SPECIAL INSPECTION OF STEEL CONSTRUCTION-WELDING IS REQUIRED. |
| 07/17/2026 | Wood I Joist Designs shall be submitted to the Registered Design Professional in Responsible Charge (RDPIRC), who shall review them and the submit them to the Building Official with a notation indicating that the deferred submittal documents have been reviewed and found to be in general conformance with the building design. Deferred submittal items shall not be installed until the deferred submittal documents have been approved by the Building Official. |