Permit: TC-COM-0625-01277
Permit Details
Apply Date:
06/30/2025
Applicant:
Brandon Goldstein
Description:
Concrete slab only for securing equipment
Permit Reviews
Permit Number - TC-COM-0625-01277
Permit Status: Complete
Permit Description: Concrete slab only for securing equipment
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/01/2025 | ADMINISTRATIVE v.2 | 10/01/2025 | APPROVED |
| 07/07/2025 | COMMERCIAL REVIEW - FULL v.1 | 07/25/2025 | REQUIRES RESUBMIT |
| 09/26/2025 | ADMINISTRATIVE v.1 | 09/26/2025 | REQUIRES RESUBMIT |
| 09/24/2025 | COMMERCIAL REVIEW - FULL v.3 | 09/26/2025 | APPROVED |
| 07/30/2025 | COMMERCIAL REVIEW - FULL v.2 | 08/19/2025 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0625-01277
Permit Status: Complete
Permit Description: Concrete slab only for securing equipment
| Date | Description | Comments |
|---|---|---|
| 07/07/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0625-01277
Permit Description: Concrete slab only for securing equipment
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/07/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | Contractor provided photos and special certificate. | |
| 10/07/2025 | ENGR Engineering Final | Passed | ||
| 10/07/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 10/07/2025 | COT - LCBU - Preslab | Passed | ||
| 10/30/2025 | COT - LCBU - Building Final | Passed | 10/30/25 passed equipment bolted to pad and shut offs in place |