Permit Details

Status:
Issued
Type:
Commercial Building
Address NEW:
7313 E ROSEWOOD ST
Apply Date:
06/16/2025
Applicant:
Colton Lloyd
Description:
New 2 story office building

Permit Reviews

Permit Number - TC-COM-0625-01161
Permit Status: Issued
Permit Description: New 2 story office building
Start Date Submittal Complete Date Status  
07/30/2025 COMMERCIAL REVIEW - FULL v.2 08/15/2025 REQUIRES RESUBMIT Review Details
08/28/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/02/2025 APPROVED Review Details
06/17/2025 COMMERCIAL REVIEW - FULL v.1 07/15/2025 REQUIRES RESUBMIT Review Details
01/28/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 02/24/2026 APPROVED Review Details
08/25/2025 COMMERCIAL REVIEW - FULL v.3 08/28/2025 APPROVED Review Details
06/22/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 07/06/2026 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0625-01161
Permit Status: Issued
Permit Description: New 2 story office building
Total Outstanding Activity Conditions - 17
Date Name
08/11/2025 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
08/28/2025 AIR BALANCING REPORT IS REQUIRED.
08/28/2025 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
08/28/2025 Elevator Designs must be submitted and approved prior to ...
08/28/2025 ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
08/28/2025 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
08/28/2025 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
08/28/2025 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
08/28/2025 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
08/28/2025 Masonry Inspection Report submittal review is required.
08/28/2025 Post-Installed Anchor Inspection Report is required.
08/28/2025 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
08/28/2025 SPECIAL INSPECTION FOR STRUCTURAL STEEL IS REQUIRED
08/28/2025 Stair Designs must be submitted and approved prior to...
08/28/2025 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
08/28/2025 WATER STERILIZATION REPORT IS REQUIRED.
08/28/2025 Prior to project being finalized or CofO being issued, applicant must revise Development Package to correct square footage discrepancies, incorrect building height, and addition of a bus shelter (per email from EHamblin).

Conditions

Permit Number - TC-COM-0625-01161
Permit Status: Issued
Permit Description: New 2 story office building
Date Description Comments
06/17/2025 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
08/11/2025 An Outdoor Lighting Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. https://www.tucsonaz.gov/files/sharedassets/public/v/1/city-services/planning-development-services/documents/special_inspection_certificate_odl.pdf
06/17/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
06/17/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.
08/28/2025 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0625-01161
Permite Description: New 2 story office building
Total Outstanding Inspections - 12
Last Inspection Date Description Inspector Results Comments
10/24/2025 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass Toe-down from Stairwell One to elevator.
11/21/2025 COT - HCBU - Stem Wall/Retaining Wall N/A Partial Pass west side and part of the north side.
12/09/2025 COT - HCEL - Electrical Underground N/A Partial Pass East side of building
01/20/2026 COT - HCBU - Masonry Pregrout N/A Partial Pass Stair B and Elevator: Top out
02/26/2026 COT - HCPL - Sewer N/A Partial Pass From building to clean out three
12/10/2025 COT - HCPL - Plumbing Intermediate N/A Partial Pass From building to start of sewer.
06/26/2026 COT - HCBU - Interior Shear Bracing N/A Partial Pass Level one.
07/27/2026 COT - HCEL - Electrical Above Ceiling N/A Partial Pass 2 patios on west side.
06/17/2026 COT - HCEL - Electrical Intermediate N/A Partial Pass Level one, walls.
03/09/2026 COT - HCBU - Framing N/A Partial Pass Level One, West side, exterior walls.
12/22/2025 COT - HCEL - Grounding/Bonding N/A Canceled
08/17/2026 COT - HCPL - Plumbing Roof Drains N/A Canceled

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0625-01161
Permit Description: New 2 story office building
Total Completed Inspections - 12
Date Description Inspector Results Comments
11/18/2025 COT - HCBU - Excavation/Rebar/Zoning Passed
11/25/2025 COT - HCBU - Stem Wall/Retaining Wall Passed
12/02/2025 COT - HCPL - Rough Soil Passed
12/10/2025 COT - HCEL - Electrical Underground Passed
12/22/2025 COT - HCBU - Preslab Passed
03/12/2026 COT - HCPL - Sewer Passed
04/09/2026 COT - HCPL - Yard Water Line Passed
06/01/2026 COT - HCBU - Roof Nailing Passed
08/14/2026 BULD - Electrical Clearance Passed TEP CLEARANCE: ECO
08/14/2026 COT - HCEL - Grounding/Bonding Passed
08/18/2026 COT - HCPL - Plumbing Roof Drains Passed
08/25/2026 COT - HCBU - Exterior Clips/Sheathing Passed