Permit: TC-COM-0624-01199
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
7355 S HOUGHTON RD BLDG 0 UNIT 109
Address NEW:
7355 S HOUGHTON RD BLDG 0 UNIT 109
Apply Date:
06/24/2024
Applicant:
Kelly Agnor
Description:
4,448 tenant remodel project for Action Behavior Centers professional office for therapy. 400000.00
Permit Reviews
Permit Number - TC-COM-0624-01199
Permit Status: Complete
Permit Description: 4,448 tenant remodel project for Action Behavior Centers professional office for therapy. 400000.00
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/27/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 12/30/2024 | APPROVED |
| 06/24/2024 | COMMERCIAL REVIEW - FULL v.1 | 08/06/2024 | REQUIRES RESUBMIT |
| 10/09/2024 | COMMERCIAL REVIEW - FULL v.3 | 10/22/2024 | APPROVED |
| 12/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/18/2024 | REQUIRES RESUBMIT |
| 08/13/2024 | COMMERCIAL REVIEW - FULL v.2 | 09/13/2024 | REQUIRES RESUBMIT |
| 10/22/2024 | RESTAMP - COMMERCIAL v.1 | 10/29/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0624-01199
Permit Status: Complete
Permit Description: 4,448 tenant remodel project for Action Behavior Centers professional office for therapy. 400000.00
| Date | Description | Comments |
|---|---|---|
| 07/26/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 08/05/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 08/05/2024 | This project requires the completion of a Fire Construction Permit PRIOR TO FINALING this permit. | |
| 08/05/2024 | An Operator's License must be applied for with the State, the absence of this license shall void this building permit. Information to the applicant. | |
| 08/05/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0624-01199
Permite Description: 4,448 tenant remodel project for Action Behavior Centers professional office for therapy. 400000.00
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2024 | COT - FCON - Alarm - Final | N/A | Not Applicable | |
| 12/13/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | NOT APPLICABLE--No gas onsite. |
| 12/13/2024 | BULD - Electrical Clearance | N/A | Not Applicable | NOT APPLICABLE--Electrical power was never disconnected from site. |
| 12/11/2024 | COT - HCBU - TCO | N/A | Re-inspection required | 12-11-24, not ready for TCO. Missing plumbing fixtures, receptacle covers, and other minor details. Contractor will reschedule when ready. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0624-01199
Permit Description: 4,448 tenant remodel project for Action Behavior Centers professional office for therapy. 400000.00
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/31/2024 | COT - LCPL - Rough Soil | Passed | ||
| 11/07/2024 | COT - LCBU - Framing | Passed | ||
| 11/08/2024 | COT - LCPL - Plumbing Intermediate | Passed | 11/8/24: Plumbing rough in is complete. Okay to install drywall on open side of walls. | |
| 12/04/2024 | COT - LCEL - Electrical Above Ceiling | Passed | 12/4/24: Electrical trim out in walls and ceiling is 99% complete. Electrician is working on installing all light switches and covers, receptacle covers, and installation of seismic wires on grid ceiling lights. All above ceiling boxes are properly labeled. | |
| 12/04/2024 | COT - LCME - Mechanical Intermediate | Passed | 12/4/24: HVAC workers are installing seismic wire on all registers, all flex ductwork is properly supported. | |
| 12/04/2024 | COT - LCEL - Electrical Intermediate | Passed | 12/4/24: Electrical trim out in walls and ceiling is 99% complete. Electrician is working on installing all light switches and covers, receptacle covers, and installation of seismic wires on grid ceiling lights. All above ceiling boxes are properly labeled. | |
| 12/11/2024 | COT - FCON - Sprinkler - Final | Passed | ||
| 12/12/2024 | COT - FCON - Fire - Final | Passed | ||
| 12/13/2024 | COT - LCPL - Plumbing Final | Passed | Construction is completed per plans and specifications. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Okay to issue a Certificate of Occupancy for this permit. | |
| 12/13/2024 | COT - LCME - Mechanical Final | Passed | Construction is completed per plans and specifications. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Okay to issue a Certificate of Occupancy for this permit. | |
| 12/13/2024 | COT - LCEL - Electrical Final | Passed | Construction is completed per plans and specifications. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Okay to issue a Certificate of Occupancy for this permit. | |
| 12/13/2024 | COT - LCBU - Building Final | Passed | Construction is completed per plans and specifications. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Okay to issue a Certificate of Occupancy for this permit. | |
| 12/13/2024 | COT - HCBU - TCO | Passed | 12/13/24: Construction is completed per plans and specifications. All mechanical, electrical, and plumbing fixtures are installed and fully operational. Okay to issue a Level 4 Certificate of Occupancy for this permit. |