Permit: TC-COM-0624-01171
Permit Details
Apply Date:
06/19/2024
Applicant:
alex enoch
Description:
Remodel of the hotel lobby and Porte Cochere
Permit Reviews
Permit Number - TC-COM-0624-01171
Permit Status: Inspections
Permit Description: Remodel of the hotel lobby and Porte Cochere
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/14/2025 | COMMERCIAL REVIEW - FULL v.3 | 05/22/2025 | REQUIRES RESUBMIT |
| 06/18/2025 | COMMERCIAL REVIEW - FULL v.4 | 06/23/2025 | REQUIRES RESUBMIT |
| 06/20/2024 | COMMERCIAL REVIEW - FULL v.1 | 07/29/2024 | REQUIRES RESUBMIT |
| 06/25/2025 | COMMERCIAL REVIEW - FULL v.5 | 06/26/2025 | APPROVED |
| 06/26/2025 | RESTAMP - COMMERCIAL v.1 | 07/01/2025 | APPROVED |
| 12/02/2024 | COMMERCIAL REVIEW - FULL v.2 | 12/20/2024 | REQUIRES RESUBMIT |
| 12/16/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 12/18/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0624-01171
Permit Status: Inspections
Permit Description: Remodel of the hotel lobby and Porte Cochere
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 05/22/2025 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
| 06/18/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 06/18/2025 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0624-01171
Permit Status: Inspections
Permit Description: Remodel of the hotel lobby and Porte Cochere
| Date | Description | Comments |
|---|---|---|
| 07/01/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 12/02/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 12/19/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0624-01171
Permite Description: Remodel of the hotel lobby and Porte Cochere
Total Outstanding Inspections - 10
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/24/2025 | COT - LCPL - Rough Soil | N/A | Re-inspection required | 2" line has negative slope. |
| 08/26/2025 | COT - LCEL - Electrical Above Ceiling | N/A | Not Applicable | |
| 08/26/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 12/04/2025 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 12/10/2025 | COT - LCEL - Electrical Final | N/A | Partial Pass | Ok for Level Three for Reception and Elevator Landing areas. |
| 12/10/2025 | COT - LCPL - Plumbing Final | N/A | Partial Pass | Ok for Level Three for Reception and Elevator Landing areas. |
| 12/15/2025 | COT - FCON - Fire - Final | N/A | Partial Pass | Ok for Level 3 TCO for Reception area and Landings. |
| 12/11/2025 | COT - HCBU - TCO | N/A | Partial Pass | Partial pass pending chlorination report |
| COT - FCON - Sprinkler - Final | N/A | Not Ready | ||
| 12/31/2025 | COT - LCBU - Building Final | N/A | Re-inspection required | 1-Install doors. 2-Install hand rails. |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-0624-01171
Permit Description: Remodel of the hotel lobby and Porte Cochere
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2025 | COT - LCPL - Rough Soil | Passed | ||
| 07/29/2025 | COT - HCEL - Electrical Underground | Passed | Low voltage, new panel location, millwork conduits schedule 40 in place. Okay to backfill progress areas. 7/29/2025 | |
| 07/31/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
| 08/01/2025 | COT - LCBU - Preslab | Passed | ||
| 08/26/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 08/26/2025 | COT - LCBU - Framing | Passed | ||
| 08/26/2025 | COT - LCME - Mechanical Intermediate | Passed | ||
| 08/26/2025 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 09/12/2025 | COT - LCBU - Roof Nailing | Passed | drywall | |
| 12/04/2025 | COT - LCME - Mechanical Final | Passed | ||
| 12/12/2025 | COT - FCON - Alarm - Final | Passed | ||
| 12/31/2025 | ENGR Engineering Final | Passed | ||
| 12/31/2025 | TRSP - ROW - Final/Close-Out | Passed |