Permit: TC-COM-0623-01607
Permit Details
Apply Date:
06/29/2023
Applicant:
Gabriel Caron
Description:
4 BAY Carport, CP1 (NO Utilities such as Electrical work on this permit)
Permit Reviews
Permit Number - TC-COM-0623-01607
Permit Status: Complete
Permit Description: 4 BAY Carport, CP1 (NO Utilities such as Electrical work on this permit)
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/20/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/20/2024 | REQUIRES RESUBMIT |
06/30/2023 | COMMERCIAL REVIEW - FULL v.1 | 08/07/2023 | APPROVED |
04/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 04/12/2024 | APPROVED |
04/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 04/01/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0623-01607
Permit Status: Complete
Permit Description: 4 BAY Carport, CP1 (NO Utilities such as Electrical work on this permit)
Date | Description | Comments |
---|---|---|
06/30/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
03/12/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES REPORT IS REQUIRED TO BE SUBMITTED. | |
03/12/2024 | SPECIAL INSPECTION FOR WELDING REPORT IS REQUIRED TO BE SUBMITTED. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0623-01607
Permit Description: 4 BAY Carport, CP1 (NO Utilities such as Electrical work on this permit)
Total Completed Inspections - 5
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/07/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
12/07/2023 | COT - LCBU - Preslab | Passed | ||
01/30/2024 | COT - LCBU - Framing | Passed | ||
02/05/2024 | COT - LCBU - Building Final | Passed | ||
02/08/2024 | ENGR Engineering Final | Passed | All cantaliver covered car bays (1) 4 bay (2) 5 bay (16) 6 bay and (3) 8 bay sections thru out site are completed and electrical has been inspected by building inspections dept. |