Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
06/28/2023
Applicant:
Barry Kitay
Description:
INTERIOR IMProVEMENTS FOR A WHITE SHELL

Permit Reviews

Permit Number - TC-COM-0623-01602
Permit Status: Complete
Permit Description: INTERIOR IMProVEMENTS FOR A WHITE SHELL
Start Date Submittal Complete Date Status  
06/29/2023 COMMERCIAL REVIEW - FULL v.1 07/28/2023 APPROVED Review Details
02/26/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/04/2024 APPROVED Review Details
01/25/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/25/2024 APPROVED Review Details

Conditions

Permit Number - TC-COM-0623-01602
Permit Status: Complete
Permit Description: INTERIOR IMProVEMENTS FOR A WHITE SHELL
Date Description Comments
07/03/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
07/03/2023 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0623-01602
Permite Description: INTERIOR IMProVEMENTS FOR A WHITE SHELL
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
09/19/2023 COT - HCBU - Framing N/A Partial Pass Walls and hard lids.
09/26/2023 COT - HCBU - Building Progress N/A Partial Pass 9/26/23: interior shear bracing per plan (5/8 type x throughout) passed.
09/19/2023 COT - HCEL - Electrical Progress N/A Partial Pass Walls and hard lids.
09/19/2023 COT - HCME - Mechanical Progress N/A Partial Pass Walls and hard lids.
09/19/2023 COT - HCPL - Plumbing Progress N/A Partial Pass Walls and hard lids.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0623-01602
Permit Description: INTERIOR IMProVEMENTS FOR A WHITE SHELL
Total Completed Inspections - 25
Date Description Inspector Results Comments
08/31/2023 COT - HCPL - Rough Soil Passed
09/26/2023 COT - HCBU - Interior Shear Bracing Passed 9/26/23: interior shear bracing per plan (5/8 type x throughout) passed.
09/26/2023 COT - HCBU - Firewall/Fire Barrier/Firestop Passed 9/26/23: interior shear bracing per plan (5/8 type x throughout) passed.
10/31/2023 COT - HCBU - Building Above Ceiling Passed
10/31/2023 COT - HCEL - Electrical Above Ceiling Passed
10/31/2023 COT - HCME - Mechanical Above Ceiling Passed
10/31/2023 COT - HCPL - Plumbing Above Ceiling Passed
11/01/2023 BULD - Electrical Clearance Passed Suite 116.
03/20/2024 COT - FCON - Fire - Final Passed
03/20/2024 COT - FCON - Sprinkler - Final Passed
03/20/2024 ENGR Engineering Final Passed
03/20/2024 COT - HCBU - Framing Passed
03/20/2024 COT - HCEL - Electrical Final Passed
03/20/2024 COT - HCBU - Building Progress Passed
03/20/2024 TRSP - ROW - Final/Close-Out Passed
03/20/2024 COT - BULD - SWG Clearance Passed
03/21/2024 COT - HCBU - CofO Passed
04/04/2024 COT - HCEL - Electrical Progress Passed
04/04/2024 COT - HCEL - Grounding/Bonding Passed
04/04/2024 COT - HCME - Mechanical Final Passed
04/04/2024 COT - HCME - Mechanical Progress Passed
04/04/2024 COT - HCME - Venting Passed
04/04/2024 COT - HCPL - Plumbing Final Passed
04/04/2024 COT - HCPL - Plumbing Progress Passed
04/04/2024 COT - HCBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
FINAL REPORT 2402-115 PHILLIP'S PLUMBING-2024-02-20_V1.PDF DOCUMENTS VIEW
SUITE 116 - BALANCE REPORT_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-1_PLAN SET_V1.PDF DOCUMENTS VIEW