Permit: TC-COM-0623-01455
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
2816 N CAMPBELL AV
Address NEW:
2816 N CAMPBELL AV
Apply Date:
06/07/2023
Applicant:
Richard Collins
Description:
Interior Remodel
Permit Reviews
Permit Number - TC-COM-0623-01455
Permit Status: Complete
Permit Description: Interior Remodel
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/07/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/17/2023 | APPROVED |
| 10/23/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/24/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0623-01455
Permit Status: Complete
Permit Description: Interior Remodel
| Date | Description | Comments |
|---|---|---|
| 07/17/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 07/10/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0623-01455
Permite Description: Interior Remodel
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/12/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 10/11/2023 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 10/11/2023 | COT - LCBU - Building Final | N/A | Re-inspection required | 1-Flush valve is on wrong side. 2-Toilet seat is not open front. 3-Need protection for lav plumbing. 4-Install toilet paper dispenser. |
| 10/11/2023 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | 1-Trap for lav has unlisted parts. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0623-01455
Permit Description: Interior Remodel
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/05/2023 | ENGR Engineering Final | Passed | ||
| 09/01/2023 | TRSP - ROW - Final/Close-Out | Passed | ||
| 09/05/2023 | COT - LCBU - Building Progress | Passed | ||
| 09/05/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 09/05/2023 | COT - LCPL - Rough Soil | Passed | ||
| 09/07/2023 | COT - LCBU - Preslab | Passed | ||
| 09/07/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 09/07/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 09/07/2023 | COT - LCBU - Framing | Passed | 9/7/23: backing added passed framing | |
| 10/11/2023 | COT - FCON - Fire - Final | Passed | ||
| 10/11/2023 | COT - FCON - Sprinkler - Final | Passed | ||
| 10/11/2023 | COT - LCEL - Electrical Final | Passed | ||
| 10/12/2023 | COT - LCBU - Building Final | Passed | ||
| 10/12/2023 | COT - LCPL - Plumbing Final | Passed |