Permit Details

Status:
Inspections
Type:
Commercial Building
Address NEW:
2200 E BROADWAY BL
Apply Date:
05/20/2026
Applicant:
TANJA WEESE
Description:
INSTALL 1 NEW SERVICE ENTRANCE SECTION AND 1 NEW DC EV FAST CHARGER

Permit Reviews

Permit Number - TC-COM-0526-00739
Permit Status: Inspections
Permit Description: INSTALL 1 NEW SERVICE ENTRANCE SECTION AND 1 NEW DC EV FAST CHARGER
Start Date Submittal Complete Date Status  
05/20/2026 COMMERCIAL PDSD SIMPLE REVIEW v.1 05/20/2026 APPROVED Review Details

Conditions

Permit Number - TC-COM-0526-00739
Permit Status: Inspections
Permit Description: INSTALL 1 NEW SERVICE ENTRANCE SECTION AND 1 NEW DC EV FAST CHARGER
Date Description Comments
05/20/2026 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-COM-0526-00739
Permite Description: INSTALL 1 NEW SERVICE ENTRANCE SECTION AND 1 NEW DC EV FAST CHARGER
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
08/03/2026 COT - LCEL - Electrical Final N/A Partial Pass 8-3-26: partial pass pending transformer installation and verifying proper operation of equipment.

Completed Inspections

Permit Status: Inspections
Permit Number: TC-COM-0526-00739
Permit Description: INSTALL 1 NEW SERVICE ENTRANCE SECTION AND 1 NEW DC EV FAST CHARGER
Total Completed Inspections - 3
Date Description Inspector Results Comments
06/24/2026 COT - LCEL - Electrical Underground Passed
08/03/2026 BULD - Electrical Clearance Passed 8-3-26: okay to install meter and energize system for EV. INCR Clearance issued to TEP
08/03/2026 COT - LCEL - Electrical Intermediate Passed 8-3-26: intermediates approved.