Permit: TC-COM-0525-00906
Permit Details
Apply Date:
05/05/2025
Applicant:
Barbara Brown
Description:
Remodel existing drive through for Angie's Prime
Permit Reviews
Permit Number - TC-COM-0525-00906
Permit Status: Complete
Permit Description: Remodel existing drive through for Angie's Prime
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/18/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/22/2025 | APPROVED |
| 05/08/2025 | COMMERCIAL REVIEW - FULL v.1 | 06/04/2025 | REQUIRES RESUBMIT |
| 06/16/2025 | RESTAMP - COMMERCIAL v.1 | 06/23/2025 | APPROVED |
| 06/04/2025 | COMMERCIAL REVIEW - FULL v.2 | 06/16/2025 | APPROVED |
| 10/07/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/08/2025 | APPROVED |
| 09/17/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/18/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0525-00906
Permit Status: Complete
Permit Description: Remodel existing drive through for Angie's Prime
| Date | Description | Comments |
|---|---|---|
| 06/16/2025 | AIR BALANCING REPORT IS REQUIRED. | |
| 05/08/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 05/30/2025 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. | |
| 06/16/2025 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0525-00906
Permite Description: Remodel existing drive through for Angie's Prime
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/23/2025 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | OK to two-side all walls except kitchen. OK to one-side kitchen; provide sealed letter from EOR for 3/4" gas piping in Kitchen wall; proceed at own risk. Obtain revision for kitchen gas piping. |
| 07/23/2025 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
| 07/23/2025 | COT - LCBU - Framing | N/A | Partial Pass | OK to two-side all walls except kitchen. OK to one-side kitchen; provide sealed letter from EOR for 3/4" gas piping in Kitchen wall; proceed at own risk. Obtain revision for kitchen gas piping. |
| 09/26/2025 | BULD - Electrical Clearance | N/A | Not Applicable | |
| 09/26/2025 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 09/17/2025 | COT - FCON - Alarm - Final | N/A | Re-inspection required | Annual inspection report shall be provided showing no deficiencies. |
| 09/17/2025 | COT - FCON - Fire - Final | N/A | Re-inspection required | Annual reports for the fire alarm and sprinklers shall be provided, kitchen hood shall be tied into the fire alarm, exit discharge lights shall be repaired, places of assembly permit shall be applied for. |
| COT - FCON - Hood System - Final | N/A | Not Ready | Hood shall be tied into the fire alarm. | |
| COT - FCON - Sprinkler - Final | N/A | Not Ready | Annual inspection shall be completed, two heads are too close together in front of the pass through, ceiling shall be intact, some escutcheons are missing |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0525-00906
Permit Description: Remodel existing drive through for Angie's Prime
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/08/2025 | COT - LCPL - Rough Soil | Passed | ||
| 07/10/2025 | COT - LCBU - Preslab | Passed | ||
| 07/23/2025 | COT - LCEL - Electrical Intermediate | Passed | ||
| 07/24/2025 | COT - LCEL - Electrical Underground | Passed | ||
| 08/13/2025 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 08/13/2025 | COT - LCME - Mechanical Intermediate | Passed | ||
| 08/13/2025 | COT - LCBU - Framing | Passed | ||
| 08/28/2025 | COT - LCEL - Electrical Above Ceiling | Passed | ||
| 09/11/2025 | COT - LCME - Kitchen Hood | Passed | ||
| 09/26/2025 | COT - LCBU - Building Final | Passed | ||
| 09/26/2025 | COT - LCEL - Electrical Final | Passed | ||
| 09/26/2025 | COT - LCME - Mechanical Final | Passed | ||
| 09/26/2025 | COT - LCPL - Plumbing Final | Passed | ||
| 09/26/2025 | ENGR Engineering Final | Passed | No exterior work performed. | |
| 09/26/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 09/30/2025 | COT - FCON - Alarm - Final | Passed | ||
| 09/30/2025 | COT - FCON - Fire - Final | Passed | ||
| 09/30/2025 | COT - FCON - Hood System - Final | Passed | ||
| 09/30/2025 | COT - FCON - Sprinkler - Final | Passed |