Permit Details

Status:
Inspections
Type:
Commercial Building
Address NEW:
707 E LEE ST UNIT G
Apply Date:
05/05/2025
Applicant:
Alex Lee
Description:
SCOPE OF WORK CONSISTS OF REPLACING EVAPORATIVE COOLER WITH PACKAGE ROOF TOP HEAT PUMP AND UPGRADING ELECTRIC PANEL IN UNIT G

Permit Reviews

Permit Number - TC-COM-0525-00899
Permit Status: Inspections
Permit Description: SCOPE OF WORK CONSISTS OF REPLACING EVAPORATIVE COOLER WITH PACKAGE ROOF TOP HEAT PUMP AND UPGRADING ELECTRIC PANEL IN UNIT G
Start Date Submittal Complete Date Status  
05/08/2025 COMMERCIAL REVIEW - LIMITED v.1 05/23/2025 APPROVED Review Details

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-COM-0525-00899
Permite Description: SCOPE OF WORK CONSISTS OF REPLACING EVAPORATIVE COOLER WITH PACKAGE ROOF TOP HEAT PUMP AND UPGRADING ELECTRIC PANEL IN UNIT G
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
06/17/2025 COT - HCME - Mechanical Intermediate N/A Not Ready
06/17/2025 COT - HCEL - Electrical Intermediate N/A Not Ready Registers need to be blocked on three sides and wires are loose without a box to contain them and terminated in the soffit area. Please install a box and make it accessible for any wires that are capped and stowed
06/20/2025 COT - LCPL - Plumbing Final N/A Not Applicable
07/25/2025 COT - BULD - SWG Clearance N/A Re-inspection required 7.25.25
Gas line is not under pressure test

Completed Inspections

Permit Status: Inspections
Permit Number: TC-COM-0525-00899
Permit Description: SCOPE OF WORK CONSISTS OF REPLACING EVAPORATIVE COOLER WITH PACKAGE ROOF TOP HEAT PUMP AND UPGRADING ELECTRIC PANEL IN UNIT G
Total Completed Inspections - 6
Date Description Inspector Results Comments
06/20/2025 COT - FCON - Fire - Final Passed
06/20/2025 COT - LCBU - Building Final Passed
06/20/2025 COT - LCEL - Electrical Final Passed
06/20/2025 COT - LCME - Mechanical Final Passed
06/20/2025 ENGR Engineering Final Passed Site is clean and safe. In accordance with plans.
08/01/2025 COT - BULD - SWG Clearance Passed Ok to set gas meter and begin service