Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0524-00773
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
250 N MAGUIRE AV UNIT 219
Address NEW:
250 N MAGUIRE AV UNIT 219
Apply Date:
05/01/2024
Applicant:
ATUL JAIN
Description:
Remodel 3 units to be ADA accessible
Permit Reviews
Permit Number - TC-COM-0524-00773
Permit Status: Complete
Permit Description: Remodel 3 units to be ADA accessible
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/06/2024 | COMMERCIAL REVIEW - FULL v.1 | 06/04/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0524-00773
Permit Status: Complete
Permit Description: Remodel 3 units to be ADA accessible
| Date | Description | Comments |
|---|---|---|
| 06/04/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0524-00773
Permite Description: Remodel 3 units to be ADA accessible
Total Outstanding Inspections - 14
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/13/2025 | COT - HCBU - Building Above Ceiling | N/A | Re-inspection required | 3/13/25: Mechanical ducts must be extended to new walls, demo mechanical must be sealed, electrical receptacles missing at kitchen and dining room, smoke detectors required throughout, plumbing not complete, NOT READY |
| 03/13/2025 | COT - HCBU - Framing | N/A | Re-inspection required | 3/13/25: Mechanical ducts must be extended to new walls, demo mechanical must be sealed, electrical receptacles missing at kitchen and dining room, smoke detectors required throughout, plumbing not complete, NOT READY |
| 03/13/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Re-inspection required | 3/13/25: Mechanical ducts must be extended to new walls, demo mechanical must be sealed, electrical receptacles missing at kitchen and dining room, smoke detectors required throughout, plumbing not complete, NOT READY |
| 03/13/2025 | COT - HCME - Mechanical Above Ceiling | N/A | Re-inspection required | 3/13/25: Mechanical ducts must be extended to new walls, demo mechanical must be sealed, electrical receptacles missing at kitchen and dining room, smoke detectors required throughout, plumbing not complete, NOT READY |
| 03/13/2025 | COT - HCME - Mechanical Intermediate | N/A | Re-inspection required | 3/13/25: Mechanical ducts must be extended to new walls, demo mechanical must be sealed, electrical receptacles missing at kitchen and dining room, smoke detectors required throughout, plumbing not complete, NOT READY |
| 03/13/2025 | COT - HCME - Mechanical Progress | N/A | Re-inspection required | 3/13/25: Mechanical ducts must be extended to new walls, demo mechanical must be sealed, electrical receptacles missing at kitchen and dining room, smoke detectors required throughout, plumbing not complete, NOT READY |
| 03/13/2025 | COT - HCPL - Plumbing Above Ceiling | N/A | Not Ready | 3/13/25: Mechanical ducts must be extended to new walls, demo mechanical must be sealed, electrical receptacles missing at kitchen and dining room, smoke detectors required throughout, plumbing not complete, NOT READY |
| 03/13/2025 | COT - HCPL - Plumbing Intermediate | N/A | Re-inspection required | 3/13/25: Mechanical ducts must be extended to new walls, demo mechanical must be sealed, electrical receptacles missing at kitchen and dining room, smoke detectors required throughout, plumbing not complete, NOT READY |
| 03/13/2025 | COT - HCPL - Plumbing Progress | N/A | Re-inspection required | 3/13/25: Mechanical ducts must be extended to new walls, demo mechanical must be sealed, electrical receptacles missing at kitchen and dining room, smoke detectors required throughout, plumbing not complete, NOT READY |
| 07/23/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Applicable | |
| 07/21/2025 | COT - HCPL - Plumbing Final | N/A | Partial Pass | Unit 419. |
| 07/21/2025 | COT - HCBU - Building Final | N/A | Partial Pass | Unit 419. |
| 07/21/2025 | COT - HCEL - Electrical Final | N/A | Partial Pass | Unit 419. |
| 07/21/2025 | COT - HCME - Mechanical Final | N/A | Partial Pass | Unit 419. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0524-00773
Permit Description: Remodel 3 units to be ADA accessible
Total Completed Inspections - 22