Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0523-01358
Permit Details
Apply Date:
05/23/2023
Applicant:
Melbourne Ames
Description:
TENANT IMPROVEMENT TO EXISTING BUILDING, NO ADDED SQUARE FOOTAGE, WORK INCLUDES ARCHITECTURAL, MECHANICAL, ELECTRICAL AND PLUMBING.
Permit Reviews
Permit Number - TC-COM-0523-01358
Permit Status: Complete
Permit Description: TENANT IMPROVEMENT TO EXISTING BUILDING, NO ADDED SQUARE FOOTAGE, WORK INCLUDES ARCHITECTURAL, MECHANICAL, ELECTRICAL AND PLUMBING.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/13/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/20/2024 | APPROVED |
08/09/2023 | COMMERCIAL REVIEW - FULL v.1 | 08/15/2023 | APPROVED |
08/02/2023 | RESTAMP - COMMERCIAL v.1 | 08/03/2023 | APPROVED |
07/03/2023 | COMMERCIAL REVIEW - FULL v.2 | 08/02/2023 | APPROVED |
09/25/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/25/2023 | REQUIRES RESUBMIT |
05/25/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/27/2023 | REQUIRES RESUBMIT |
10/09/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 10/10/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0523-01358
Permit Status: Complete
Permit Description: TENANT IMPROVEMENT TO EXISTING BUILDING, NO ADDED SQUARE FOOTAGE, WORK INCLUDES ARCHITECTURAL, MECHANICAL, ELECTRICAL AND PLUMBING.
Date | Description | Comments |
---|---|---|
08/02/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
03/13/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0523-01358
Permite Description: TENANT IMPROVEMENT TO EXISTING BUILDING, NO ADDED SQUARE FOOTAGE, WORK INCLUDES ARCHITECTURAL, MECHANICAL, ELECTRICAL AND PLUMBING.
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/22/2023 | COT - HCBU - Building Progress | N/A | Partial Pass | 8/22/23 ok to continue |
08/22/2023 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 8/22/23 electrical outlets on gypsum board walls need to be grounded everything else looks good |
08/22/2023 | COT - HCME - Mechanical Progress | N/A | Partial Pass | 8/22/23 Looks good, hangers on hvac secured properly |
08/22/2023 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 8/22/23 ok to continue no leaks |
08/29/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | 8/29/23: not applicable no gas on site |
09/14/2023 | COT - HCME - Mechanical Final | N/A | Not Ready | 9/14/23: waiting for air balance report |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0523-01358
Permit Description: TENANT IMPROVEMENT TO EXISTING BUILDING, NO ADDED SQUARE FOOTAGE, WORK INCLUDES ARCHITECTURAL, MECHANICAL, ELECTRICAL AND PLUMBING.
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/08/2023 | COT - HCPL - Rough Soil | Passed | Partial pass. Looked at water closet and floor sink. 3" pipe Under pressure no leaks. Pending lavatory. Okay to backfill shading required. 8/8/2023 | |
08/22/2023 | COT - HCBU - Framing | Passed | 8/21/23 ok to board up | |
08/29/2023 | BULD - Electrical Clearance | Passed | TEP ECO | |
09/07/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
09/07/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
09/07/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
09/07/2023 | COT - HCME - Venting | Passed | ||
09/07/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
09/14/2023 | COT - HCME - Mechanical Above Ceiling | Passed | ||
09/15/2023 | ENGR Engineering Final | Passed | ||
09/14/2023 | TRSP - ROW - Final/Close-Out | Passed | ||
09/15/2023 | COT - HCME - Mechanical Final | Passed | ||
09/15/2023 | COT - HCPL - Plumbing Final | Passed | ||
09/15/2023 | COT - HCEL - Electrical Final | Passed | ||
09/18/2023 | COT - FCON - Fire - Final | Passed | ||
09/18/2023 | COT - FCON - Sprinkler - Final | Passed | ||
09/19/2023 | COT - HCBU - Building Final | Passed | ||