Permit: TC-COM-0523-01272
Permit Details
Apply Date:
05/15/2023
Applicant:
Fabien Reille
Description:
The Remote Gate Management (RGM) System Scope of Work is summarized as follows: 1. Install Advanced License Plate Readers (ALPR’s) x 6 (3 inbound/3 outbound). 2. Construct concrete pads x 6 (10’ x 10’ x 7”). 3. Install 25’ TQ pole for pole-mounted Bosch cameras x 3 with CAT6 cable from IDF room. 4. Manage installation of 25’ TQ pole with concrete reinforced bases (10’ x 2’ diameter) for Bosch cameras (amazon selected vendor). 5. Install RGM bollards x 8 (4 inbound/ 4 outbound). 6. Install barrier arm gates x 2. 7. Install guard rails. 8. Relocate existing fencing and provide new where needed. 9. Install new pole-mounted signage x 2. 10. Paint ground markings – water-based paint or acrylic with glass beads.
Permit Reviews
Permit Number - TC-COM-0523-01272
Permit Status: Complete
Permit Description: The Remote Gate Management (RGM) System Scope of Work is summarized as follows:
1. Install Advanced License Plate Readers (ALPR’s) x 6 (3 inbound/3 outbound).
2. Construct concrete pads x 6 (10’ x 10’ x 7”).
3. Install 25’ TQ pole for pole-mounted Bosch cameras x 3 with CAT6 cable from IDF room.
4. Manage installation of 25’ TQ pole with concrete reinforced bases (10’ x 2’ diameter) for Bosch cameras (amazon selected vendor).
5. Install RGM bollards x 8 (4 inbound/ 4 outbound).
6. Install barrier arm gates x 2.
7. Install guard rails.
8. Relocate existing fencing and provide new where needed.
9. Install new pole-mounted signage x 2.
10. Paint ground markings – water-based paint or acrylic with glass beads.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/07/2023 | COMMERCIAL REVIEW - FULL v.3 | 08/03/2023 | REQUIRES RESUBMIT |
05/22/2023 | COMMERCIAL REVIEW - FULL v.2 | 06/23/2023 | REQUIRES RESUBMIT |
04/22/2024 | COMMERCIAL REVIEW - FULL v.1 | 04/22/2024 | REQUIRES RESUBMIT |
02/05/2024 | COMMERCIAL REVIEW - FULL v.2 | 02/06/2024 | REQUIRES RESUBMIT |
10/23/2023 | RESTAMP - COMMERCIAL v.1 | 10/30/2023 | APPROVED |
06/14/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/14/2024 | REQUIRES RESUBMIT |
04/30/2024 | COMMERCIAL REVIEW - FULL v.2 | 05/06/2024 | APPROVED |
09/28/2023 | COMMERCIAL REVIEW - FULL v.4 | 10/23/2023 | APPROVED |
06/24/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/24/2024 | REQUIRES RESUBMIT |
05/18/2023 | COMMERCIAL REVIEW - FULL v.1 | 05/18/2023 | REQUIRES RESUBMIT |
03/25/2024 | COMMERCIAL REVIEW - FULL v.3 | 04/12/2024 | APPROVED |
01/08/2024 | COMMERCIAL REVIEW - FULL v.1 | 02/05/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0523-01272
Permit Status: Complete
Permit Description: The Remote Gate Management (RGM) System Scope of Work is summarized as follows:
1. Install Advanced License Plate Readers (ALPR’s) x 6 (3 inbound/3 outbound).
2. Construct concrete pads x 6 (10’ x 10’ x 7”).
3. Install 25’ TQ pole for pole-mounted Bosch cameras x 3 with CAT6 cable from IDF room.
4. Manage installation of 25’ TQ pole with concrete reinforced bases (10’ x 2’ diameter) for Bosch cameras (amazon selected vendor).
5. Install RGM bollards x 8 (4 inbound/ 4 outbound).
6. Install barrier arm gates x 2.
7. Install guard rails.
8. Relocate existing fencing and provide new where needed.
9. Install new pole-mounted signage x 2.
10. Paint ground markings – water-based paint or acrylic with glass beads.
Date | Description | Comments |
---|---|---|
10/30/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0523-01272
Permite Description: The Remote Gate Management (RGM) System Scope of Work is summarized as follows:
1. Install Advanced License Plate Readers (ALPR’s) x 6 (3 inbound/3 outbound).
2. Construct concrete pads x 6 (10’ x 10’ x 7”).
3. Install 25’ TQ pole for pole-mounted Bosch cameras x 3 with CAT6 cable from IDF room.
4. Manage installation of 25’ TQ pole with concrete reinforced bases (10’ x 2’ diameter) for Bosch cameras (amazon selected vendor).
5. Install RGM bollards x 8 (4 inbound/ 4 outbound).
6. Install barrier arm gates x 2.
7. Install guard rails.
8. Relocate existing fencing and provide new where needed.
9. Install new pole-mounted signage x 2.
10. Paint ground markings – water-based paint or acrylic with glass beads.
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/29/2024 | COT - LCEL - Electrical Underground | N/A | Partial Pass | 4/30/24: Southeast (outbound lanes) (5) 3" Conduits for ALPR systems at north outbound lane complete and ok to backfill. 5/1/24: southeast (outbound lanes) (4) 3" conduit from ALPR tri-pod to NEMA north outbound lane next to security structure complete ok to backfill 5/8/24: southeast (outbound lane) (4) 3" conduits from ALPR tri-pod to nema On east side of security structure complete. Ok to backfill 5/29/24: Northwest (inbound lanes) 2 south lanes electrical underground per plans ok to proceed. |
06/18/2024 | COT - HCBU - TCO | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0523-01272
Permit Description: The Remote Gate Management (RGM) System Scope of Work is summarized as follows:
1. Install Advanced License Plate Readers (ALPR’s) x 6 (3 inbound/3 outbound).
2. Construct concrete pads x 6 (10’ x 10’ x 7”).
3. Install 25’ TQ pole for pole-mounted Bosch cameras x 3 with CAT6 cable from IDF room.
4. Manage installation of 25’ TQ pole with concrete reinforced bases (10’ x 2’ diameter) for Bosch cameras (amazon selected vendor).
5. Install RGM bollards x 8 (4 inbound/ 4 outbound).
6. Install barrier arm gates x 2.
7. Install guard rails.
8. Relocate existing fencing and provide new where needed.
9. Install new pole-mounted signage x 2.
10. Paint ground markings – water-based paint or acrylic with glass beads.
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/06/2024 | COT - LCBU - Preslab | Passed | ||
06/04/2024 | COT - LCEL - Electrical Underground | Passed | 4/30/24: Southeast (outbound lanes) (5) 3" Conduits for ALPR systems at north outbound lane complete and ok to backfill. 5/1/24: southeast (outbound lanes) (4) 3" conduit from ALPR tri-pod to NEMA north outbound lane next to security structure complete ok to backfill 5/8/24: southeast (outbound lane) (4) 3" conduits from ALPR tri-pod to nema On east side of security structure complete. Ok to backfill 5/29/24: Northwest (inbound lanes) 2 south lanes electrical underground per plans ok to proceed. 6/4/24: north west (inbound lanes) 1 on north side of security office electrical underground per plan |
|
06/17/2024 | COT - FCON - Fire - Final | Passed | ||
06/18/2024 | COT - LCBU - Building Final | Passed | 5/21/24: Ok for TCO level 4 on south side only. 6/18/24: CofO passed |
|
06/18/2024 | ENGR Engineering Final | Passed | Super had to move one stop sign and pole out from the center of the circulation path. | |
06/18/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
06/18/2024 | COT - LCEL - Electrical Final | Passed | ||
06/18/2024 | COT - LCEL - Grounding/Bonding | Passed |