Permit: TC-COM-0425-00861
Permit Details
Apply Date:
04/29/2025
Applicant:
Kelly Rehm
Description:
The Canary Systems PV system will consist of 30 Silab 520W modules and metal decking mounted on a new steel parking canopy. Microinverters will supply power through an existing TEP service.
Permit Reviews
Permit Number - TC-COM-0425-00861
Permit Status: Complete
Permit Description: The Canary Systems PV system will consist of 30 Silab 520W modules and metal decking mounted on a new steel parking canopy. Microinverters will supply power through an existing TEP service.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/04/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/05/2025 | APPROVED |
| 04/29/2025 | COMMERCIAL REVIEW - FULL v.1 | 05/23/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0425-00861
Permit Status: Complete
Permit Description: The Canary Systems PV system will consist of 30 Silab 520W modules and metal decking mounted on a new steel parking canopy. Microinverters will supply power through an existing TEP service.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 05/19/2025 | SPECIAL INSPECTION OFCOLD-FORMED STEEL FRAMING IS REQUIRED. |
| 05/19/2025 | SPECIAL INSPECTION OF FABRICATORS IS REQUIRED |
| 05/19/2025 | SPECIAL INSPECTION OF STRUCTURAL STEEL IS REQUIRED. (Welding and Bolting) |
| 06/05/2025 | General Inspection / Foundations / Embeds |
Conditions
Permit Number - TC-COM-0425-00861
Permit Status: Complete
Permit Description: The Canary Systems PV system will consist of 30 Silab 520W modules and metal decking mounted on a new steel parking canopy. Microinverters will supply power through an existing TEP service.
| Date | Description | Comments |
|---|---|---|
| 06/03/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 05/19/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0425-00861
Permite Description: The Canary Systems PV system will consist of 30 Silab 520W modules and metal decking mounted on a new steel parking canopy. Microinverters will supply power through an existing TEP service.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/22/2025 | BULD - Electrical Clearance | N/A | Deferred | 8-10-25: okay to reconnect power on meter 159474910 at 998 S. Cherry Avenue. Verbal clearance given to TEP at 810AM. 8/22/25: DGC TEP CLEARANCE |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0425-00861
Permit Description: The Canary Systems PV system will consist of 30 Silab 520W modules and metal decking mounted on a new steel parking canopy. Microinverters will supply power through an existing TEP service.
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/11/2025 | COT - LCBU - Excavation/Rebar/Zoning | Passed | Approved (2) column footings and ufer ground, okay for concrete placement | |
| 06/11/2025 | COT - CSOL - Grounding/Bonding Solar Project | Passed | ||
| 06/24/2025 | COT - CSOL - Electrical Underground Solar Project | Passed | ||
| 08/11/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
| 08/11/2025 | COT - CSOL - Electrical Final Solar Project | Passed | Meter #159447920, CODE: DGC | |
| 08/11/2025 | COT - FCON - Fire - Final | Passed | ||
| 08/11/2025 | COT - LCBU - Building Final | Passed | ||
| 08/11/2025 | ENGR Engineering Final | Passed | ||
| 08/11/2025 | COT - CSOL - Electrical Intermediate Solar Project | Passed | ||
| 08/11/2025 | COT - LCBU - Framing | Passed | ||
| 08/11/2025 | COT - CSOL - Outdoor Lighting Solar Project | Passed |