Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
04/14/2025
Applicant:
Amy Cotner
Description:
Speculative TI buildout in unoccupied Shell under separate permit.

Permit Reviews

Permit Number - TC-COM-0425-00736
Permit Status: Complete
Permit Description: Speculative TI buildout in unoccupied Shell under separate permit.
Start Date Submittal Complete Date Status  
04/16/2025 COMMERCIAL REVIEW - FULL v.1 05/08/2025 REQUIRES RESUBMIT Review Details
06/06/2025 COMMERCIAL REVIEW - FULL v.2 06/10/2025 APPROVED Review Details
05/15/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/19/2026 APPROVED Review Details
05/20/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/21/2026 APPROVED Review Details
03/25/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/06/2026 APPROVED Review Details
06/10/2025 RESTAMP - COMMERCIAL v.1 06/23/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-0425-00736
Permit Status: Complete
Permit Description: Speculative TI buildout in unoccupied Shell under separate permit.
Date Description Comments
04/16/2025 BLDG 1 UNIT 1140 Needs to be added to cover sheet as part of the address to reflect this permit application.
04/16/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
07/02/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0425-00736
Permite Description: Speculative TI buildout in unoccupied Shell under separate permit.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
01/28/2026 COT - HCME - Mechanical Intermediate N/A Partial Pass Hard duct in place at office areas. Pending flex lines ties to registers. 1/28/2026
04/09/2026 COT - BULD - SWG Clearance N/A Not Applicable 4-9-26: not applicable.
12/05/2025 COT - HCEL - Electrical Progress N/A Partial Pass 12-5-25: in wall electrical at demising wall verified per plans. Okay to continue with TI at progress areas.
12/10/2025 COT - HCBU - Building Progress N/A Partial Pass 12/10/2025 Screw Re-inspection of demising wall approved. Okay to proceed progress areas.
11/17/2025 COT - HCPL - Plumbing Progress N/A Partial Pass 11-17-25: underground plumbing verified per plans. Okay to backfill-shading required.
Note: schedule a dowel & vapor barrier inspection prior to pour back.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0425-00736
Permit Description: Speculative TI buildout in unoccupied Shell under separate permit.
Total Completed Inspections - 23
Date Description Inspector Results Comments
02/17/2026 COT - HCEL - Electrical Intermediate Passed 2-17-26: in wall electrical and above ceiling approved. Okay to continue with cons at progress areas.
02/17/2026 COT - HCPL - Plumbing Intermediate Passed 2-17-26: DWV/Domestic in wall under test-plumbing per plans.
03/03/2026 COT - HCBU - Framing Passed 3-3-26: previously inspected & approved.
03/03/2026 COT - HCPL - Plumbing Above Ceiling Passed 3-3-26: approved.
03/04/2026 BULD - Electrical Clearance Passed 3-4-26: okay to energize Suite 1140-panel #4. INCR Clearance issued to TEP.
03/26/2026 COT - HCME - Mechanical Intermediate Passed 3-26-26: mechanical intermediate approved.
04/23/2026 COT - HCBU - Building Above Ceiling Passed 4-23-26: building above ceiling approved.
04/23/2026 COT - HCME - Mechanical Above Ceiling Passed 4-23-26: mechanical above ceiling approved.
04/23/2026 COT - HCEL - Electrical Above Ceiling Passed 4-23-26: electrical above ceiling approved.
04/27/2026 COT - HCME - Mechanical Progress Passed 4-27-26: approved.
04/27/2026 COT - HCEL - Electrical Progress Passed 4-27-26: approved-pending finals.
04/27/2026 COT - HCBU - Building Progress Passed 4-27-26: approved.
04/27/2026 COT - HCPL - Plumbing Progress Passed 4-27-26: approved-pending finals.
04/27/2026 ENGR Engineering Final Passed Site is safe and complete in accordance with approved plans.
04/27/2026 TRSP - ROW - Final/Close-Out Passed
05/13/2026 COT - HCME - Mechanical Final Passed 5-13-26: mechanical final approved.
05/13/2026 COT - HCEL - Electrical Final Passed 5-13-26: electrical final approved.
05/14/2026 COT - FCON - Sprinkler - Final Passed
05/14/2026 COT - FCON - Fire - Final Passed
05/14/2026 COT - FCON - Alarm - Final Passed
05/15/2026 COT - HCBU - Building Final Passed 5-15-26: building final approved. All conditions have been satisfied- okay to apply for C of O.
05/15/2026 COT - HCBU - CofO Passed 5-15-26: building final approved. All conditions have been satisfied- okay to apply for C of O.
05/15/2026 COT - HCPL - Plumbing Final Passed 5-15-26: plumbing final approved.

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL (SSRS).PDF DOCUMENTS VIEW
LOFC_LETTEROFCOMPLETION (SSRS).PDF DOCUMENTS VIEW
DREXEL COMMERCE CENTER SUITE 1140_V1.PDF DOCUMENTS VIEW
26E0260_1 TURNER 05 14 2026 0856-2026-05-15_V1.PDF DOCUMENTS VIEW
DREXEL TORQUE03232026_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-DREXEL CC TI BUILDING 1 - SUITE 1140_V2.PDF DOCUMENTS VIEW
COMCHECK-SUITE 1140 - VLMK SIGNED_V2.PDF DOCUMENTS VIEW
DREXEL CC TI STRUCTURAL CALCULATIONS_SEALED_V2.PDF DOCUMENTS VIEW