Permit: TC-COM-0423-01130
Permit Details
Apply Date:
04/24/2023
Applicant:
John Woodin
Description:
Interior Remodel - Brewery
Permit Reviews
Permit Number - TC-COM-0423-01130
Permit Status: Complete
Permit Description: Interior Remodel - Brewery
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/12/2023 | COMMERCIAL REVIEW - FULL v.3 | 07/14/2023 | REQUIRES RESUBMIT |
| 07/19/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/19/2023 | REQUIRES RESUBMIT |
| 07/19/2023 | COMMERCIAL REVIEW - FULL v.2 | 07/20/2023 | APPROVED |
| 04/28/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/01/2023 | REQUIRES RESUBMIT |
| 05/31/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/31/2024 | APPROVED |
| 07/17/2023 | RESTAMP - COMMERCIAL v.1 | 07/18/2023 | REQUIRES RESUBMIT |
| 06/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/05/2024 | APPROVED |
| 11/03/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/13/2023 | APPROVED |
| 06/07/2023 | COMMERCIAL REVIEW - FULL v.2 | 07/11/2023 | REQUIRES RESUBMIT |
| 11/15/2023 | COMMERCIAL REVIEW - FULL v.1 | 12/14/2023 | APPROVED |
| 06/17/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/17/2024 | APPROVED |
| 07/14/2023 | COMMERCIAL REVIEW - FULL v.4 | 07/17/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0423-01130
Permit Status: Complete
Permit Description: Interior Remodel - Brewery
| Date | Description | Comments |
|---|---|---|
| 05/30/2024 | AIR BALANCING REPORT IS REQUIRED. | |
| 05/30/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. | |
| 05/30/2024 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. | |
| 05/30/2024 | Local FIRE Department INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION | |
| 05/30/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
| 05/30/2024 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
| 05/30/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0423-01130
Permite Description: Interior Remodel - Brewery
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/22/2024 | COT - HCBU - TCO | N/A | Partial Pass | Phase III is complete. Ok to make application for Temporary Certificate of Occupancy, Level #3 (equipment and training personnel and to begin brewing). No public access. |
| COT - FCON - Alarm - Final | N/A | Not Ready | ||
| COT - FCON - Fire - Final | N/A | Not Ready | alarm was not finished. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0423-01130
Permit Description: Interior Remodel - Brewery
Total Completed Inspections - 19
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/22/2024 | COT - BULD - SWG Clearance | Passed | resend SWG clearance | |
| 10/06/2023 | COT - LCPL - Yard Water Line | Passed | Ok to cover main water line. | |
| 10/18/2023 | COT - LCPL - Plumbing Intermediate | Passed | Underground plumbing is complete and under water test. Okay to shade pipes and backfill trenches. | |
| 10/27/2023 | COT - LCBU - Preslab | Passed | ||
| 01/09/2024 | BULD - Electrical Clearance | Passed | Approved service panel upgrade, INCR Clearance is required to TEP for the permanent power 1/22/24 resent clearance |
|
| 02/01/2024 | COT - LCBU - Framing | Passed | ||
| 01/23/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
| 01/23/2024 | COT - LCEL - Grounding/Bonding | Passed | ||
| 02/22/2024 | COT - LCPL - Gas Pressure Test | Passed | Approved gas piping and pressure test, SWG Clearance is required | |
| 04/30/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
| 04/30/2024 | COT - LCME - Mechanical Final | Passed | ||
| 05/22/2024 | COT - LCPL - Plumbing Final | Passed | ||
| 05/22/2024 | COT - LCEL - Electrical Final | Passed | ||
| 05/22/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
| 06/17/2024 | COT - FCON - Sprinkler - Final | Passed | ||
| 06/18/2024 | COT - FCON - Alarm - Final | Passed | ||
| 06/18/2024 | COT - FCON - Fire - Final | Passed | ||
| 06/18/2024 | COT - HCBU - CofO | Passed | Need Fire final: OK for a Level #4 Temporary Certificate of Occupancy. Fire inspection complete. EWS | |
| 06/18/2024 | COT - LCBU - Building Final | Passed | Need Fire Final: OK for Level #4 TCO. Fire final passed on 6/18/2024 EWS |