Permit Details

Status:
Complete
Type:
Commercial Building
Address:
9800 E RITA RD
Apply Date:
04/12/2023
Applicant:
Cary Broschat
Description:
50 kw (AC) solar covered parking canopy installation

Permit Reviews

Permit Number - TC-COM-0423-01041
Permit Status: Complete
Permit Description: 50 kw (AC) solar covered parking canopy installation
Start Date Submittal Complete Date Status  
10/16/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/23/2023 APPROVED Review Details
03/21/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/01/2024 APPROVED Review Details
04/18/2023 COMMERCIAL REVIEW - FULL v.1 05/19/2023 APPROVED Review Details
06/05/2023 COMMERCIAL REVIEW - FULL v.1 07/05/2023 APPROVED Review Details

Conditions

Permit Number - TC-COM-0423-01041
Permit Status: Complete
Permit Description: 50 kw (AC) solar covered parking canopy installation
Date Description Comments
05/19/2023 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
05/19/2023 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
05/19/2023 SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED.
05/19/2023 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
05/19/2023 SPECIAL INSPECTION FOR WELDING IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0423-01041
Permite Description: 50 kw (AC) solar covered parking canopy installation
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
08/25/2023 COT - LCEL - Electrical Underground N/A Partial Pass 8/25/23: all electric underground conduit stubbed up at the two columns approved to cover.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0423-01041
Permit Description: 50 kw (AC) solar covered parking canopy installation
Total Completed Inspections - 10
Date Description Inspector Results Comments
08/22/2023 COT - LCBU - Excavation/Rebar/Zoning Passed
09/06/2023 COT - LCBU - Framing Passed Approved PV structure per SI
09/08/2023 COT - CSOL - Electrical Underground Solar Project Passed Approved underground conduits from building to PV structure, okay to backfill and concrete encase
09/26/2023 COT - LCEL - Outdoor Lighting Passed Approved lighting under canopy
10/06/2023 COT - LCBU - Building Final Passed
10/06/2023 COT - LCEL - Electrical Final Passed
10/06/2023 BULD - Electrical Clearance Passed
10/06/2023 COT - LCEL - Grounding/Bonding Passed
10/06/2023 ENGR Engineering Final Passed
10/06/2023 COT - LCEL - Electrical Intermediate Passed

Documents

File Name Document Type  
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
29.23.1621 PURPLE HEART PARK SOLAR CANOPIES WELDING REPORT-2024-03-21_V1.PDF DOCUMENTS VIEW
COT - PUPLE HEART - SI FINAL-2023-10-16_V1.PDF DOCUMENTS VIEW
COT - PURPLE HEART - FINAL SI REPORT_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-COT - PURPLE HEART PARK POOL_COMBINED SET_230601_V1.PDF DOCUMENTS VIEW
PHP DEV EMAIL_V1.PDF DOCUMENTS VIEW
TC-COM-0423-01041 - REVISION LETTER_V1.PDF DOCUMENTS VIEW
CONS-COT - PURPLE HEART PARK POOL_SEALED SET_COMBINED_230412_V1.PDF DOCUMENTS VIEW
COT - PURPLE HEART PARK POOL_STRUC CALCS_V1.PDF DOCUMENTS VIEW
COT - PURPLE HEART PARK POOL_SPECIAL INSPECTIONS_SIGNED-2023-04-12_V1.PDF DOCUMENTS VIEW
COT - PURPLE HEART PARK POOL_GEOTECH_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW