Permit Details

Status:
Complete
Type:
Commercial Building
Address:
615 W ALTURAS ST
Address NEW:
615 W ALTURAS ST
Apply Date:
04/11/2023
Applicant:
Brad Davis
Description:
THIS IS FOR THE CONSTRUCTION OF A NEW 2,388 SF SINGLE STORY COMMUNITY BUILDING.

Permit Reviews

Permit Number - TC-COM-0423-01034
Permit Status: Complete
Permit Description: THIS IS FOR THE CONSTRUCTION OF A NEW 2,388 SF SINGLE STORY COMMUNITY BUILDING.
Start Date Submittal Complete Date Status  
08/01/2023 COMMERCIAL REVIEW - FULL v.3 08/03/2023 APPROVED Review Details
06/12/2023 COMMERCIAL REVIEW - FULL v.2 06/29/2023 REQUIRES RESUBMIT Review Details
06/12/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/17/2025 APPROVED Review Details
08/03/2023 RESTAMP - COMMERCIAL v.1 08/05/2023 APPROVED Review Details
04/18/2023 COMMERCIAL REVIEW - FULL v.1 05/12/2023 REQUIRES RESUBMIT Review Details
04/08/2025 COMMERCIAL REVIEW - FULL REVISION v.1 04/24/2025 APPROVED Review Details
06/03/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/03/2025 REQUIRES RESUBMIT Review Details
06/11/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 06/12/2025 APPROVED Review Details
03/04/2024 COMMERCIAL REVIEW - FULL v.2 03/19/2024 APPROVED Review Details
03/19/2024 RESTAMP - COMMERCIAL v.1 03/20/2024 APPROVED Review Details
01/19/2024 COMMERCIAL REVIEW - FULL v.1 02/27/2024 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-0423-01034
Permit Status: Complete
Permit Description: THIS IS FOR THE CONSTRUCTION OF A NEW 2,388 SF SINGLE STORY COMMUNITY BUILDING.
Date Description Comments
06/03/2024 AIR BALANCING REPORT IS REQUIRED.
04/24/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
06/03/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
06/03/2024 Masonry Inspection Report submittal review is required.
06/03/2024 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
08/01/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
06/03/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
06/03/2024 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0423-01034
Permite Description: THIS IS FOR THE CONSTRUCTION OF A NEW 2,388 SF SINGLE STORY COMMUNITY BUILDING.
Total Outstanding Inspections - 8
Last Inspection Date Description Inspector Results Comments
02/14/2025 COT - HCBU - Stem Wall/Retaining Wall N/A Not Applicable
03/03/2025 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Not Applicable
03/03/2025 COT - HCPL - Gas Final N/A Not Applicable
03/03/2025 COT - HCPL - Gas Pressure Test N/A Not Applicable
03/03/2025 COT - BULD - SWG Clearance N/A Not Applicable
07/08/2024 COT - HCEL - Electrical Underground N/A Partial Pass 7/5/24: partial electrical underground at community center electrical room only.
10/16/2024 COT - HCBU - Framing N/A Not Ready
04/07/2025 BULD - Electrical Clearance N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0423-01034
Permit Description: THIS IS FOR THE CONSTRUCTION OF A NEW 2,388 SF SINGLE STORY COMMUNITY BUILDING.
Total Completed Inspections - 28
Date Description Inspector Results Comments
06/03/2024 COT - HCEL - Grounding/Bonding Passed UFER installed at community building. 5/30/2024
06/27/2024 COT - HCPL - Rough Soil Passed
06/27/2024 COT - HCPL - Sewer Passed
06/27/2024 COT - HCPL - Yard Water Line Passed
08/06/2024 COT - HCBU - Excavation/Rebar/Zoning Passed
08/06/2024 COT - HCBU - Preslab Passed
10/16/2024 COT - HCBU - Exterior Clips/Sheathing Passed
10/16/2024 COT - HCBU - Roof Nailing Passed
03/03/2025 COT - HCEL - Electrical Underground Passed
03/27/2025 COT - HCBU - Framing Passed
03/27/2025 COT - HCBU - Building Progress Passed
03/27/2025 COT - HCEL - Electrical Intermediate Passed
03/27/2025 COT - HCME - Mechanical Intermediate Passed
03/27/2025 COT - HCME - Venting Passed
03/27/2025 COT - HCPL - Plumbing Intermediate Passed
04/29/2025 COT - HCEL - Electrical Above Ceiling Passed
04/29/2025 COT - HCPL - Plumbing Above Ceiling Passed
05/02/2025 COT - HCBU - Building Above Ceiling Passed
05/02/2025 COT - HCME - Mechanical Above Ceiling Passed
05/19/2025 BULD - Electrical Clearance Passed
06/09/2025 COT - HCPL - Plumbing Final Passed
06/10/2025 COT - HCEL - Electrical Final Passed
06/10/2025 COT - HCEL - Outdoor Lighting Passed
06/10/2025 COT - HCME - Mechanical Final Passed
06/11/2025 COT - HCBU - Building Final Passed
06/18/2025 COT - FCON - Fire - Final Passed
06/18/2025 ENGR Engineering Final Passed
06/18/2025 TRSP - ROW - Final/Close-Out Passed