Permit: TC-COM-0423-01031
Permit Details
Apply Date:
04/11/2023
Applicant:
Corky Poster
Description:
EXISTING BLDG 7, REHAB, 676 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Permit Reviews
Permit Number - TC-COM-0423-01031
Permit Status: Issued
Permit Description: EXISTING BLDG 7, REHAB, 676 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/27/2023 | COMMERCIAL REVIEW - FULL v.1 | 05/30/2023 | REQUIRES RESUBMIT |
06/27/2023 | COMMERCIAL REVIEW - FULL v.2 | 07/03/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0423-01031
Permit Status: Issued
Permit Description: EXISTING BLDG 7, REHAB, 676 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Outstanding Activity Conditions - 14
Date | Name |
---|---|
06/16/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. |
06/16/2023 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
06/16/2023 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
06/16/2023 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
06/16/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
06/16/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
06/16/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
06/16/2023 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
06/16/2023 | Verify that Permit #P23SD00041 - Milagro on Oracle - Public Sewer is issued and all fees are paid – Waste water receipt |
06/16/2023 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
06/16/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
06/16/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
06/26/2023 | Prior to project being finalized applicant must provide new water easement recordation information |
07/31/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - TC-COM-0423-01031
Permit Status: Issued
Permit Description: EXISTING BLDG 7, REHAB, 676 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Date | Description | Comments |
---|---|---|
06/16/2023 | Please contact Pima County Addressing to resolve your addressing issue related to FILL IN THIS SPACE. Addressing@pima.gov or 520-724-9512 | |
04/27/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
06/16/2023 | NESHAP Permit is required. (Utilized with commercial demolition permits) |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0423-01031
Permite Description: EXISTING BLDG 7, REHAB, 676 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/28/2024 | COT - BULD - SWG Clearance | N/A | Partial Pass | No gas clearance required at this time. This inspection is for interior framing to include interior framing for Building #8. |
08/30/2024 | COT - LCPL - Plumbing Final | N/A | Not Ready | Scheduled for site sewer, see site for results |
08/30/2024 | COT - HCPL - Sewer | N/A | Partial Pass | Partial for site sewer line north side of casitas running east west, clean outs to go |
10/01/2024 | BULD - Electrical Clearance | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0423-01031
Permit Description: EXISTING BLDG 7, REHAB, 676 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/21/2024 | COT - LCBU - Preslab | Passed | ||
05/01/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
05/01/2024 | COT - LCEL - Electrical Intermediate | Passed | ||
05/01/2024 | COT - LCEL - Electrical Underground | Passed | ||
05/01/2024 | COT - LCEL - Grounding/Bonding | Passed | ||
05/02/2024 | COT - BULD - SWG Clearance | Passed |