Permit: TC-COM-0423-01027
Permit Details
Apply Date:
04/11/2023
Applicant:
Corky Poster
Description:
EXISTING BLDG 2, REHAB, 3245 SF, 4 UNITS - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Permit Reviews
Permit Number - TC-COM-0423-01027
Permit Status: Issued
Permit Description: EXISTING BLDG 2, REHAB, 3245 SF, 4 UNITS - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/27/2023 | COMMERCIAL REVIEW - FULL v.1 | 05/30/2023 | REQUIRES RESUBMIT |
06/27/2023 | COMMERCIAL REVIEW - FULL v.2 | 07/03/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0423-01027
Permit Status: Issued
Permit Description: EXISTING BLDG 2, REHAB, 3245 SF, 4 UNITS - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Outstanding Activity Conditions - 10
Date | Name |
---|---|
12/18/2024 | AIR BALANCING REPORT IS REQUIRED. |
12/18/2024 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
12/18/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
12/18/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
12/18/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
12/18/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
12/18/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
12/18/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
12/18/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
12/18/2024 | Prior to project being finalized applicant must provide new water easement recordation information |
Conditions
Permit Number - TC-COM-0423-01027
Permit Status: Issued
Permit Description: EXISTING BLDG 2, REHAB, 3245 SF, 4 UNITS - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Date | Description | Comments |
---|---|---|
06/16/2023 | Please contact Pima County Addressing to resolve your addressing issue related to FILL IN THIS SPACE. Addressing@pima.gov or 520-724-9512 | |
04/27/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
12/18/2024 | Verify that Permit #P23SD00041 - Milagro on Oracle - Public Sewer is issued and all fees are paid – Waste water receipt | |
06/16/2023 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0423-01027
Permite Description: EXISTING BLDG 2, REHAB, 3245 SF, 4 UNITS - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Outstanding Inspections - 9
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
COT - LCEL - Electrical Underground | N/A | Requested | ||
COT - LCEL - Grounding/Bonding | N/A | Requested | ||
01/25/2024 | COT - LCBU - Preslab | N/A | Partial Pass | DETAIL #119. S501 BUILDING #10. TOTAL OF 24 COLUMNS. BUILDING #2-#8. 1 COLUMN PER BUILDING. BUILDING #7. EXTERIOR COLUMN DETAIL #120. BUILDING #3 NOT BUILT YET. Okay for concrete placement. 1/25/24 |
10/01/2024 | COT - LCEL - Electrical Progress | N/A | Not Applicable | |
12/13/2024 | ENGR Engineering Final | N/A | Partial Pass | Okay for TCO Level 4 Fix grab bar on east door. |
12/04/2024 | BULD - Electrical Clearance | N/A | Not Applicable | |
12/04/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
12/17/2024 | COT - FCON - Alarm - Final | N/A | Partial Pass | Fire Alarm is not complete, need report from State Elevator Inspector. |
12/17/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | Fire Alarm is not complete, need report from State Elevator Inspector. OK for TCO level 4. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0423-01027
Permit Description: EXISTING BLDG 2, REHAB, 3245 SF, 4 UNITS - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Completed Inspections - 11
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/26/2024 | COT - LCPL - Rough Soil | Passed | ||
04/29/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
04/29/2024 | COT - LCEL - Electrical Intermediate | Passed | All MEP'S approved in building #2. Okay to insulate and drywall. 4/29/2024 | |
12/19/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
12/06/2024 | COT - LCEL - Electrical Final | Passed | ||
12/06/2024 | COT - LCME - Mechanical Final | Passed | ||
12/12/2024 | COT - HCBU - TCO | Passed | OK to make application for TCO Level #4 for units #1 - #8. | |
12/12/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
12/12/2024 | COT - LCBU - Building Final | Passed | ||
12/12/2024 | COT - LCPL - Plumbing Final | Passed | ||
12/17/2024 | COT - FCON - Sprinkler - Final | Passed |