Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
04/11/2023
Applicant:
Corky Poster
Description:
EXISTING BLDG 1, REHAB, 971 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.

Permit Reviews

Permit Number - TC-COM-0423-01026
Permit Status: Complete
Permit Description: EXISTING BLDG 1, REHAB, 971 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Start Date Submittal Complete Date Status  
03/25/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/01/2025 APPROVED Review Details
01/11/2024 COMMERCIAL REVIEW - FULL v.1 02/08/2024 REQUIRES RESUBMIT Review Details
02/15/2024 RESTAMP - COMMERCIAL v.1 02/16/2024 APPROVED Review Details
04/27/2023 COMMERCIAL REVIEW - FULL v.1 05/30/2023 REQUIRES RESUBMIT Review Details
06/27/2023 COMMERCIAL REVIEW - FULL v.2 07/03/2023 APPROVED Review Details
02/12/2024 COMMERCIAL REVIEW - FULL v.2 02/15/2024 APPROVED Review Details

Conditions

Permit Number - TC-COM-0423-01026
Permit Status: Complete
Permit Description: EXISTING BLDG 1, REHAB, 971 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Date Description Comments
04/27/2023 Please contact Pima County Addressing to resolve your addressing issue related to FILL IN THIS SPACE. Addressing@pima.gov or 520-724-9512
12/18/2024 AIR BALANCING REPORT IS REQUIRED.
12/18/2024 Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents.
12/18/2024 Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents.
12/18/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
12/18/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
12/18/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
12/18/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
12/18/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
03/28/2025 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
12/18/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
03/28/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
12/18/2024 Verify that Permit #P23SD00041 - Milagro on Oracle - Public Sewer is issued and all fees are paid – Waste water receipt
12/18/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
12/18/2024 Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building.
12/18/2024 WATER STERILIZATION REPORT IS REQUIRED.
12/18/2024 Prior to project being finalized applicant must provide new water easement recordation information

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0423-01026
Permite Description: EXISTING BLDG 1, REHAB, 971 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
06/05/2024 BULD - Electrical Clearance N/A Not Ready
03/07/2024 COT - BULD - SWG Clearance N/A Not Ready
06/07/2024 COT - LCEL - Outdoor Lighting N/A Not Ready Not ready. Prior to final. 6/7/2024
12/17/2024 COT - FCON - Alarm - Final N/A Partial Pass Fire Alarm is not complete, need report from State Elevator Inspector.
12/17/2024 COT - FCON - Fire - Final N/A Partial Pass Fire Alarm is not complete, need report from State Elevator Inspector. OK for TCO level 4.
12/13/2024 ENGR Engineering Final N/A Partial Pass Okay for TCO Level 4

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0423-01026
Permit Description: EXISTING BLDG 1, REHAB, 971 SF, 1 UNIT - BLDGS 3 & 9 ARE "COMMERCIAL NEW BUILDING", BLDGS 1,2,4-8 & 10 "COMMERCIAL ADDITION/ALTERATION PERMIT". "DEMO" INCLUDED IN BLDG 9 PERMIT.
Total Completed Inspections - 18
Date Description Inspector Results Comments
03/07/2024 COT - HCPL - Rough Soil Passed Interior plumbing rough ok to backfill.
04/26/2024 COT - LCEL - Electrical Underground Passed Underground conduits to Building #1, OK to cover progress areas.
04/26/2024 COT - LCEL - Grounding/Bonding Passed
06/05/2024 COT - LCEL - Electrical Progress Passed
06/05/2024 COT - LCBU - Preslab Passed
06/07/2024 COT - LCEL - Electrical Above Ceiling Passed Insulation was removed. MEP´S APPROVED. 6/7/2024
06/07/2024 COT - LCEL - Electrical Intermediate Passed Insulation was removed. MEP´S APPROVED. 6/7/2024
12/19/2024 TRSP - ROW - Final/Close-Out Passed
12/06/2024 COT - LCEL - Electrical Final Passed
12/06/2024 COT - LCME - Mechanical Final Passed
12/12/2024 COT - HCBU - TCO Passed Ok to make application for TCO Level #4 for units #1 - #8.
12/12/2024 COT - LCEL - Outdoor Lighting Passed
12/12/2024 COT - LCBU - Building Final Passed
12/12/2024 COT - LCPL - Plumbing Final Passed
12/17/2024 COT - FCON - Sprinkler - Final Passed
01/22/2025 COT - FCON - Alarm - Final Passed
01/22/2025 COT - FCON - Fire - Final Passed
01/31/2025 ENGR Engineering Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
1.) SPECIAL INSPECTIONS_SPECIAL INSPECTION CERTIFICATE_V1.PDF DOCUMENTS VIEW
AIR BALANCE REPORT_V1.PDF DOCUMENTS VIEW
BUILDING 9_V1.PDF DOCUMENTS VIEW
ELEVATOR INSPECTION-2025-03-25_V1.PDF DOCUMENTS VIEW
LIGHTING SPECIAL INSPECTION NOTE-2025-03-25_V1.PDF DOCUMENTS VIEW
TC-COM-0423-01026 BLDG 1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
TC-COM-0423-01026 TCO 2.17.2025.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
CONS-24.22.12_MILAGRO_BUILDING 1 DRAWINGS REV. 9_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW