Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0325-00631
Permit Details
Apply Date:
03/28/2025
Applicant:
Description:
Install 400Amp 120/240v MDP to feed bldg from existing SES. Install grounding and bonding as required per code. Sturgeon is being asked to take over project from previous contractor to fix deficiencies and obtain permit to restore power to the building.
Permit Reviews
Permit Number - TC-COM-0325-00631
Permit Status: Inspections
Permit Description: Install 400Amp 120/240v MDP to feed bldg from existing SES. Install grounding and bonding as required per code. Sturgeon is being asked to take over project from previous contractor to fix deficiencies and obtain permit to restore power to the building.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/25/2025 | COMMERCIAL REVIEW - LIMITED v.2 | 08/25/2025 | REQUIRES RESUBMIT |
| 04/03/2025 | COMMERCIAL REVIEW - LIMITED v.1 | 04/18/2025 | REQUIRES RESUBMIT |
| 08/27/2025 | COMMERCIAL REVIEW - LIMITED v.3 | 08/28/2025 | APPROVED |
| 08/28/2025 | RESTAMP - COMMERCIAL v.1 | 08/28/2025 | APPROVED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0325-00631
Permite Description: Install 400Amp 120/240v MDP to feed bldg from existing SES. Install grounding and bonding as required per code. Sturgeon is being asked to take over project from previous contractor to fix deficiencies and obtain permit to restore power to the building.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/05/2025 | COT - LCEL - Electrical Underground | N/A | Not Applicable |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-0325-00631
Permit Description: Install 400Amp 120/240v MDP to feed bldg from existing SES. Install grounding and bonding as required per code. Sturgeon is being asked to take over project from previous contractor to fix deficiencies and obtain permit to restore power to the building.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/03/2025 | COT - LCEL - Electrical Intermediate | Passed | 12/3/25 Pass |
|
| 12/03/2025 | COT - LCEL - Grounding/Bonding | Passed | ||
| 12/03/2025 | BULD - Electrical Clearance | Passed | 12/3/25 TEP Clearance: INCR, Building D. |