Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Inspections
Type:
Commercial Building
Address:
7450 E 22ND ST
Address NEW:
7450 E 22ND ST
Apply Date:
03/28/2025
Applicant:
Description:
Install 400Amp 120/240v MDP to feed bldg from existing SES. Install grounding and bonding as required per code. Sturgeon is being asked to take over project from previous contractor to fix deficiencies and obtain permit to restore power to the building.

Permit Reviews

Permit Number - TC-COM-0325-00631
Permit Status: Inspections
Permit Description: Install 400Amp 120/240v MDP to feed bldg from existing SES. Install grounding and bonding as required per code. Sturgeon is being asked to take over project from previous contractor to fix deficiencies and obtain permit to restore power to the building.
Start Date Submittal Complete Date Status  
08/25/2025 COMMERCIAL REVIEW - LIMITED v.2 08/25/2025 REQUIRES RESUBMIT Review Details
04/03/2025 COMMERCIAL REVIEW - LIMITED v.1 04/18/2025 REQUIRES RESUBMIT Review Details
08/27/2025 COMMERCIAL REVIEW - LIMITED v.3 08/28/2025 APPROVED Review Details
08/28/2025 RESTAMP - COMMERCIAL v.1 08/28/2025 APPROVED Review Details

Outstanding Inspections

Permit Status: Inspections
Permit Number: TC-COM-0325-00631
Permite Description: Install 400Amp 120/240v MDP to feed bldg from existing SES. Install grounding and bonding as required per code. Sturgeon is being asked to take over project from previous contractor to fix deficiencies and obtain permit to restore power to the building.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/05/2025 COT - LCEL - Electrical Underground N/A Not Applicable

Completed Inspections

Permit Status: Inspections
Permit Number: TC-COM-0325-00631
Permit Description: Install 400Amp 120/240v MDP to feed bldg from existing SES. Install grounding and bonding as required per code. Sturgeon is being asked to take over project from previous contractor to fix deficiencies and obtain permit to restore power to the building.
Total Completed Inspections - 3
Date Description Inspector Results Comments
12/03/2025 COT - LCEL - Electrical Intermediate Passed 12/3/25
Pass
12/03/2025 COT - LCEL - Grounding/Bonding Passed
12/03/2025 BULD - Electrical Clearance Passed 12/3/25
TEP Clearance: INCR, Building D.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-TIERRA-SOL APARTMENTS 100CD 5-28-25_CKM_V2.PDF DOCUMENTS VIEW