Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
03/11/2025
Applicant:
Hector Jimenez
Description:
office tenant improvement within existing shell building. Project includes; new in-wall plumbing, mechanical and electrical work. REV1: Due to field inspectors request - several electrical sheets are required to be modified. Permit TC-COM-0325-00481 Electrical sheets; E0.1, E0.2, E1.0, E2.0, E3.0, E3.1 are being submitted at this time to reflect the required changes.

Permit Reviews

Permit Number - TC-COM-0325-00481
Permit Status: Complete
Permit Description: office tenant improvement within existing shell building. Project includes; new in-wall plumbing, mechanical and electrical work. REV1: Due to field inspectors request - several electrical sheets are required to be modified. Permit TC-COM-0325-00481 Electrical sheets; E0.1, E0.2, E1.0, E2.0, E3.0, E3.1 are being submitted at this time to reflect the required changes.
Start Date Submittal Complete Date Status  
03/12/2025 COMMERCIAL REVIEW - LIMITED v.1 03/28/2025 REQUIRES RESUBMIT Review Details
05/27/2025 RESTAMP - COMMERCIAL v.1 05/28/2025 APPROVED Review Details
08/05/2025 COMMERCIAL REVIEW - FULL REVISION v.1 08/05/2025 APPROVED Review Details
08/13/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/14/2025 APPROVED Review Details
05/19/2025 RESTAMP - COMMERCIAL v.1 05/22/2025 APPROVED Review Details
04/07/2025 COMMERCIAL REVIEW - LIMITED v.2 04/22/2025 REQUIRES RESUBMIT Review Details
05/01/2025 COMMERCIAL REVIEW - LIMITED v.3 05/19/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-0325-00481
Permit Status: Complete
Permit Description: office tenant improvement within existing shell building. Project includes; new in-wall plumbing, mechanical and electrical work. REV1: Due to field inspectors request - several electrical sheets are required to be modified. Permit TC-COM-0325-00481 Electrical sheets; E0.1, E0.2, E1.0, E2.0, E3.0, E3.1 are being submitted at this time to reflect the required changes.
Date Description Comments
03/12/2025 Please verify (SUIT/UNIT #) on Address. Construction Plan has 1141 N EL DORADO PL, Suite 205 and Permit Application has 1141 N EL DORADO PL, Bldg 3, Unit 200.
04/21/2025 AIR BALANCING REPORT IS REQUIRED.
03/12/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
03/12/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0325-00481
Permite Description: office tenant improvement within existing shell building. Project includes; new in-wall plumbing, mechanical and electrical work. REV1: Due to field inspectors request - several electrical sheets are required to be modified. Permit TC-COM-0325-00481 Electrical sheets; E0.1, E0.2, E1.0, E2.0, E3.0, E3.1 are being submitted at this time to reflect the required changes.
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
06/04/2025 BULD - Electrical Clearance N/A Not Applicable
07/21/2025 COT - LCEL - Grounding/Bonding N/A Not Applicable
06/04/2025 COT - LCPL - Plumbing Final N/A Not Ready Work incomplete
08/13/2025 COT - FCON - Alarm - Final N/A Not Applicable
07/21/2025 COT - HCBU - TCO N/A Re-inspection required Obtain Final Inspections approval

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0325-00481
Permit Description: office tenant improvement within existing shell building. Project includes; new in-wall plumbing, mechanical and electrical work. REV1: Due to field inspectors request - several electrical sheets are required to be modified. Permit TC-COM-0325-00481 Electrical sheets; E0.1, E0.2, E1.0, E2.0, E3.0, E3.1 are being submitted at this time to reflect the required changes.
Total Completed Inspections - 16
Date Description Inspector Results Comments
05/30/2025 COT - HCPL - Plumbing Intermediate Passed
05/30/2025 COT - LCBU - Framing Passed
06/02/2025 COT - LCEL - Electrical Intermediate Passed
06/10/2025 COT - LCEL - Electrical Above Ceiling Passed
06/25/2025 COT - HCBU - Building Above Ceiling Passed 6-25-25: firewall/firestop approved. Okay to continue with construction at progress areas.
06/25/2025 COT - HCBU - Firewall/Fire Barrier/Firestop Passed 6-25-25: firewall/firestop approved. Okay to continue with construction at progress areas.
07/16/2025 COT - HCEL - Electrical Above Ceiling Passed
07/16/2025 COT - HCME - Mechanical Intermediate Passed
07/16/2025 COT - HCME - Mechanical Above Ceiling Passed
07/16/2025 COT - HCPL - Plumbing Above Ceiling Passed
07/21/2025 COT - LCME - Mechanical Final Passed
07/21/2025 COT - LCPL - Plumbing Final Passed
08/13/2025 COT - FCON - Fire - Final Passed
08/13/2025 COT - FCON - Sprinkler - Final Passed
08/12/2025 COT - LCEL - Electrical Final Passed
08/13/2025 COT - LCBU - Building Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
AIR BALANCE REPORT_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
06_PLANSET_V1.PDF DOCUMENTS VIEW
05_PLANSET_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-03_PLANSET_V3.PDF DOCUMENTS VIEW