Permit: TC-COM-0325-00429
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
3125 N GERONIMO AV
Address NEW:
3125 N GERONIMO AV
Apply Date:
03/05/2025
Applicant:
Martha Johnson
Description:
The below estimate is to replace all trailer sewer lines south of main road at furthest West Point Call AZ 811 to mark all underground utilities Pull all needed permits to complete work Saw cut all needed asphalt +/- 250’- haul away from site Excavate ground as needed from each trailer sewer connection to new main sewer line Excavate ground as needed from furthest south point of road to main rd At each trailer install correct set of clean-outs to meet code Install all needed piping and fittings to accommodate new sewer installation Install tracer wire to meet code Remove old connection on main road and install clean out with drive rated cap Upon completion of new sewer line shade per code requirements Install needed caps to fill sewer for inspection Obtain inspection Make final connection on main sewer line headed east on main road Backfill and compact to a like condition Return asphalt to a like condition Please note the following: No use of sewer from trailer units during installation or connections of sewer lines No vehicles to be permitted to drive in or out of trailer community during course of work At completion of each day drive rated steal plates to be placed over dug ditches to allow tenants to return vehicles to homes and walking as needed Job duration is approximately 8-9 business days (sewer installation) asphalt and saw cut is approximately an additional 1-2 days Please attached documentation of new sewer All work holds a Ram Plumbing 2yr warranty This warranty excludes foreign objects or vandalism
Permit Reviews
Permit Number - TC-COM-0325-00429
Permit Status: Complete
Permit Description: The below estimate is to replace all trailer sewer lines south of main road at furthest West Point
Call AZ 811 to mark all underground utilities
Pull all needed permits to complete work
Saw cut all needed asphalt +/- 250’- haul away from site
Excavate ground as needed from each trailer sewer connection to new main sewer line
Excavate ground as needed from furthest south point of road to main rd
At each trailer install correct set of clean-outs to meet code
Install all needed piping and fittings to accommodate new sewer installation
Install tracer wire to meet code
Remove old connection on main road and install clean out with drive rated cap
Upon completion of new sewer line shade per code requirements
Install needed caps to fill sewer for inspection
Obtain inspection
Make final connection on main sewer line headed east on main road
Backfill and compact to a like condition
Return asphalt to a like condition
Please note the following:
No use of sewer from trailer units during installation or connections of sewer lines
No vehicles to be permitted to drive in or out of trailer community during course of work
At completion of each day drive rated steal plates to be placed over dug ditches to allow tenants to return vehicles to homes and walking as needed
Job duration is approximately 8-9 business days (sewer installation) asphalt and saw cut is approximately an additional 1-2 days
Please attached documentation of new sewer
All work holds a Ram Plumbing 2yr warranty
This warranty excludes foreign objects or vandalism
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/07/2025 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 03/14/2025 | REQUIRES RESUBMIT |
| 04/02/2025 | COMMERCIAL PDSD SIMPLE REVIEW v.2 | 04/02/2025 | APPROVED |
Conditions
Permit Number - TC-COM-0325-00429
Permit Status: Complete
Permit Description: The below estimate is to replace all trailer sewer lines south of main road at furthest West Point
Call AZ 811 to mark all underground utilities
Pull all needed permits to complete work
Saw cut all needed asphalt +/- 250’- haul away from site
Excavate ground as needed from each trailer sewer connection to new main sewer line
Excavate ground as needed from furthest south point of road to main rd
At each trailer install correct set of clean-outs to meet code
Install all needed piping and fittings to accommodate new sewer installation
Install tracer wire to meet code
Remove old connection on main road and install clean out with drive rated cap
Upon completion of new sewer line shade per code requirements
Install needed caps to fill sewer for inspection
Obtain inspection
Make final connection on main sewer line headed east on main road
Backfill and compact to a like condition
Return asphalt to a like condition
Please note the following:
No use of sewer from trailer units during installation or connections of sewer lines
No vehicles to be permitted to drive in or out of trailer community during course of work
At completion of each day drive rated steal plates to be placed over dug ditches to allow tenants to return vehicles to homes and walking as needed
Job duration is approximately 8-9 business days (sewer installation) asphalt and saw cut is approximately an additional 1-2 days
Please attached documentation of new sewer
All work holds a Ram Plumbing 2yr warranty
This warranty excludes foreign objects or vandalism
| Date | Description | Comments |
|---|---|---|
| 03/07/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0325-00429
Permit Description: The below estimate is to replace all trailer sewer lines south of main road at furthest West Point
Call AZ 811 to mark all underground utilities
Pull all needed permits to complete work
Saw cut all needed asphalt +/- 250’- haul away from site
Excavate ground as needed from each trailer sewer connection to new main sewer line
Excavate ground as needed from furthest south point of road to main rd
At each trailer install correct set of clean-outs to meet code
Install all needed piping and fittings to accommodate new sewer installation
Install tracer wire to meet code
Remove old connection on main road and install clean out with drive rated cap
Upon completion of new sewer line shade per code requirements
Install needed caps to fill sewer for inspection
Obtain inspection
Make final connection on main sewer line headed east on main road
Backfill and compact to a like condition
Return asphalt to a like condition
Please note the following:
No use of sewer from trailer units during installation or connections of sewer lines
No vehicles to be permitted to drive in or out of trailer community during course of work
At completion of each day drive rated steal plates to be placed over dug ditches to allow tenants to return vehicles to homes and walking as needed
Job duration is approximately 8-9 business days (sewer installation) asphalt and saw cut is approximately an additional 1-2 days
Please attached documentation of new sewer
All work holds a Ram Plumbing 2yr warranty
This warranty excludes foreign objects or vandalism
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/16/2025 | COT - LCPL - Sewer | Passed | ||
| 04/16/2025 | COT - LCPL - Plumbing Final | Passed | Approved approx 175' of 4" private sewer main and 3" lateral with clean out to units, 0kay to shade fill progress areas |