Permit: TC-COM-0324-00558
Permit Details
Apply Date:
03/29/2024
Applicant:
Marytine Ramos
Description:
Installation of Roof mounted 22kW PV System / Load Side tap
Permit Reviews
Permit Number - TC-COM-0324-00558
Permit Status: Issued
Permit Description: Installation of Roof mounted 22kW PV System / Load Side tap
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/01/2024 | COMMERCIAL REVIEW - FULL v.1 | 04/30/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0324-00558
Permit Status: Issued
Permit Description: Installation of Roof mounted 22kW PV System / Load Side tap
| Date | Description | Comments |
|---|---|---|
| 04/30/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0324-00558
Permit Description: Installation of Roof mounted 22kW PV System / Load Side tap
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/11/2024 | COT - LCBU - Building Final | Passed | ||
| 06/11/2024 | COT - CSOL - Electrical Final Solar Project | Passed | ||
| 06/11/2024 | COT - CSOL - Electrical Progress Solar Project | Passed | ||
| 06/11/2024 | COT - CSOL - Grounding/Bonding Solar Project | Passed | ||
| 06/11/2024 | BULD - Electrical Clearance | Passed | Approved - DGC/ DGL Clearance to TEP is required for the load-side and solar meter | |
| 06/12/2024 | ENGR Engineering Final | Passed |