Permit: TC-COM-0324-00549
Permit Details
Apply Date:
03/27/2024
Applicant:
Chris Helgeson
Description:
Classroom building 3 of previously approved phase 1 of PRCA south campus.
Permit Reviews
Permit Number - TC-COM-0324-00549
Permit Status: Issued
Permit Description: Classroom building 3 of previously approved phase 1 of PRCA south campus.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/28/2024 | COMMERCIAL REVIEW - FULL v.1 | 03/28/2024 | REQUIRES RESUBMIT |
06/26/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/27/2024 | REQUIRES RESUBMIT |
07/03/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 07/08/2024 | APPROVED |
03/28/2024 | COMMERCIAL REVIEW - FULL v.2 | 04/29/2024 | REQUIRES RESUBMIT |
06/13/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/18/2024 | REQUIRES RESUBMIT |
05/07/2024 | COMMERCIAL REVIEW - FULL v.3 | 05/13/2024 | APPROVED |
05/13/2024 | RESTAMP - COMMERCIAL v.1 | 05/15/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0324-00549
Permit Status: Issued
Permit Description: Classroom building 3 of previously approved phase 1 of PRCA south campus.
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
05/10/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
05/10/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
05/10/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Conditions
Permit Number - TC-COM-0324-00549
Permit Status: Issued
Permit Description: Classroom building 3 of previously approved phase 1 of PRCA south campus.
Date | Description | Comments |
---|---|---|
03/28/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
05/10/2024 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0324-00549
Permite Description: Classroom building 3 of previously approved phase 1 of PRCA south campus.
Total Outstanding Inspections - 6
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/15/2024 | COT - HCBU - Framing | N/A | Partial Pass | Loose shear walls at marked areas. Missing stud at south end wall of building. Kickers at interior walls not per schedule. Add anchor bolts at marked areas throughout. Correct blocking between osb. Add fire blocking where missing. 7/9/2024 7/15/24: 1st lift at masonry piers reinforcement per plan ok to proceed |
07/15/2024 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 7/15/24: 1st lift at masonry piers reinforcement per plan ok to proceed |
08/29/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
07/12/2024 | COT - HCBU - Preslab | N/A | Partial Pass | 6/13/24: reinforcement per plan at classroom footings. Ok to pour progress areas. 7/11/24: reinforcement per plan at classroom. Ok to proceed. Pending CMU pier footings. 7/12/24: reinforcement per plans at CMU pier footings ok to place concrete, |
08/30/2024 | COT - FCON - Alarm - Final | N/A | Partial Pass | Waiting on Alarm contractor to get permit for work that has already been done. Fire alarm has been tested. |
08/30/2024 | COT - FCON - Fire - Final | N/A | Re-inspection required | EM lights not working, building number, Alarm permit. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0324-00549
Permit Description: Classroom building 3 of previously approved phase 1 of PRCA south campus.
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/09/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP INCR. 7/9/2024 | |
07/09/2024 | COT - HCBU - Roof Nailing | Passed | ||
07/16/2024 | COT - HCBU - Framing | Passed | ||
07/18/2024 | COT - HCBU - Masonry Pregrout | Passed | 7/15/24: 1st lift at masonry piers reinforcement per plan ok to proceed 7/17/24: 2nd lift up to beam sit reinforcement per plan ok to proceed. 7/18/24: 3rd lift passed ok to grout. Top out passed. |
|
07/29/2024 | COT - HCPL - Plumbing Roof Drains | Passed | 7/18/24: not ready 7/29/24: roof drains under pressure and per plans ok to proceed. With insulation and drywall |
|
07/30/2024 | COT - HCBU - Interior Shear Bracing | Passed | 7/30/24: wanted drywall nailing inspection | |
08/29/2024 | COT - HCBU - Preslab | Passed | ||
08/29/2024 | COT - HCBU - Building Above Ceiling | Passed | 8/29/24: not ready properly support and seal flex duct, panel schedule and all receptacles must be made up. Roof access required. | |
08/29/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
08/29/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
08/29/2024 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
08/29/2024 | COT - HCEL - Electrical Intermediate | Passed | ||
08/29/2024 | COT - HCME - Mechanical Intermediate | Passed | ||
08/29/2024 | COT - HCPL - Plumbing Final | Passed | ||
08/29/2024 | COT - HCEL - Grounding/Bonding | Passed | ||
08/29/2024 | COT - HCEL - Electrical Underground | Passed | ||
08/30/2024 | COT - HCEL - Electrical Final | Passed | ||
08/30/2024 | COT - HCME - Mechanical Final | Passed | ||
08/30/2024 | ENGR Engineering Final | Passed | This building is a stand alone building within the confines of the 1st phase of which a TCO4 has already been given and will follow through the next phases of construction on phases 2,3,and 4. | |
09/03/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
09/03/2024 | COT - HCBU - Building Final | Passed |