Permit: TC-COM-0324-00486
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
2102 N DRAGOON ST
Address NEW:
2102 N DRAGOON ST
Apply Date:
03/19/2024
Applicant:
Cary Broschat
Description:
Install PV solar shade structure 76.5 KW dc 60 KW ac 140 modules
Permit Reviews
Permit Number - TC-COM-0324-00486
Permit Status: Complete
Permit Description: Install PV solar shade structure
76.5 KW dc 60 KW ac
140 modules
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/19/2024 | COMMERCIAL REVIEW - FULL v.1 | 04/19/2024 | APPROVED |
| 06/04/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/05/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0324-00486
Permit Status: Complete
Permit Description: Install PV solar shade structure
76.5 KW dc 60 KW ac
140 modules
| Date | Description | Comments |
|---|---|---|
| 04/19/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 04/19/2024 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. | |
| 04/19/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 04/19/2024 | SPECIAL INSPECTION FOR FABRICATION IS REQUIRED | |
| 04/19/2024 | SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0324-00486
Permit Description: Install PV solar shade structure
76.5 KW dc 60 KW ac
140 modules
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/06/2024 | COT - CSOL - Electrical Underground Solar Project | Passed | ||
| 05/06/2024 | COT - LCBU - Excavation/Rebar/Zoning | Passed | Approved (4) column foundations per plan and special inspection report, okay for concrete placement | |
| 05/17/2024 | COT - CSOL - Outdoor Lighting Solar Project | Passed | ||
| 05/17/2024 | COT - CSOL - Grounding/Bonding Solar Project | Passed | ||
| 05/17/2024 | COT - CSOL - Electrical Progress Solar Project | Passed | ||
| 05/17/2024 | COT - LCBU - Framing | Passed | ||
| 05/17/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
| 05/29/2024 | COT - CSOL - Electrical Final Solar Project | Passed | ||
| 05/31/2024 | COT - CSOL - Electrical Intermediate Solar Project | Passed | ||
| 05/31/2024 | ENGR Engineering Final | Passed | ||
| 05/31/2024 | COT - LCEL - Electrical Final | Passed | ||
| 05/31/2024 | COT - LCBU - Building Final | Passed | ||
| 05/31/2024 | BULD - Electrical Clearance | Passed | Approved - DGC Clearance to TEP is required for the solar meter |