Permit: TC-COM-0323-00877
Permit Details
Apply Date:
03/23/2023
Applicant:
Lisa Bowers
Description:
TI: Retail
Permit Reviews
Permit Number - TC-COM-0323-00877
Permit Status: Complete
Permit Description: TI: Retail
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/19/2023 | COMMERCIAL REVIEW - FULL v.2 | 05/31/2023 | REQUIRES RESUBMIT |
09/26/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/28/2023 | REQUIRES RESUBMIT |
10/03/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 10/10/2023 | APPROVED |
06/08/2023 | COMMERCIAL REVIEW - FULL v.3 | 06/08/2023 | APPROVED |
03/24/2023 | COMMERCIAL REVIEW - FULL v.1 | 04/20/2023 | REQUIRES RESUBMIT |
06/08/2023 | RESTAMP - COMMERCIAL v.1 | 06/08/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0323-00877
Permit Status: Complete
Permit Description: TI: Retail
Date | Description | Comments |
---|---|---|
09/28/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
06/08/2023 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. | |
06/08/2023 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
06/08/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
06/08/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
06/08/2023 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0323-00877
Permite Description: TI: Retail
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/01/2023 | BULD - Electrical Clearance | N/A | Canceled | CA, TEP canceled kill |
08/09/2023 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | ok to install hard lids |
07/27/2023 | COT - HCBU - Framing | N/A | Partial Pass | |
09/26/2023 | COT - HCBU - Building Final | N/A | Partial Pass | 9/21/23: TCO for full occupancy waiting on fire final to be passed for full CofO |
09/26/2023 | COT - FCON - Fire - Final | N/A | Partial Pass | 1. Ok for TCO for full occupancy. 2. Will need to replace FDC valves for building. 3. Once completed Full C of O will be issued. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0323-00877
Permit Description: TI: Retail
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/28/2023 | COT - HCBU - Preslab | Passed | Underground plumbing rough-in complete. Okay to backfill trenches, compact soil and pour concrete slab repairs. | |
07/27/2023 | COT - HCPL - Gas Pressure Test | Passed | ||
07/27/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
08/08/2023 | BULD - Electrical Clearance | Passed | Good to go to reconnect power. | |
08/09/2023 | COT - HCBU - Framing | Passed | ||
08/23/2023 | COT - BULD - SWG Clearance | Passed | Approved gas piping to rooftop HVAC units, SWG clearance is required unit 111 | |
09/14/2023 | COT - HCBU - Building Above Ceiling | Passed | ||
09/14/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | ||
09/21/2023 | COT - HCME - Mechanical Final | Passed | ||
09/21/2023 | TRSP - ROW - Final/Close-Out | Passed | ||
09/21/2023 | ENGR Engineering Final | Passed | ||
09/25/2023 | COT - HCEL - Electrical Final | Passed | ||
09/25/2023 | COT - HCPL - Plumbing Final | Passed | ||
09/25/2023 | COT - HCEL - Electrical Above Ceiling | Passed | ||
09/25/2023 | COT - HCEL - Electrical Intermediate | Passed | 9/25/23: passed by previous inspection | |
09/25/2023 | COT - HCPL - Gas Final | Passed | ||
10/30/2023 | COT - FCON - Fire - Final | Passed |