Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
03/20/2023
Applicant:
Lisa Bowers
Description:
TI: Cardiovascular Clinic

Permit Reviews

Permit Number - TC-COM-0323-00836
Permit Status: Complete
Permit Description: TI: Cardiovascular Clinic
Start Date Submittal Complete Date Status  
05/23/2023 RESTAMP - COMMERCIAL v.1 05/24/2023 APPROVED Review Details
05/12/2023 COMMERCIAL REVIEW - FULL v.2 05/23/2023 APPROVED Review Details
03/22/2023 COMMERCIAL REVIEW - FULL v.1 04/19/2023 REQUIRES RESUBMIT Review Details
01/30/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/31/2024 APPROVED Review Details
01/18/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/18/2024 APPROVED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0323-00836
Permite Description: TI: Cardiovascular Clinic
Total Outstanding Inspections - 5
Last Inspection Date Description Inspector Results Comments
COT - HCME - Mechanical Intermediate N/A Requested
09/14/2023 COT - HCPL - Plumbing Intermediate N/A Partial Pass 9/14/23: domestic water hot & cold approved. All new pvc vents approved.
01/05/2024 BULD - Electrical Clearance N/A Not Applicable
01/05/2024 COT - BULD - SWG Clearance N/A Not Applicable
03/12/2024 COT - FCON - Fire - Final N/A Partial Pass Access doors, still need to be worked out, mag locks are connected to the fire alarm.

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0323-00836
Permit Description: TI: Cardiovascular Clinic
Total Completed Inspections - 20
Date Description Inspector Results Comments
07/28/2023 COT - HCPL - Rough Soil Passed UG Plumbing, except SW corner where leak is; oK to cover elsewhere.
7/28/23: OK to cover all under slab soil pipe.
08/09/2023 COT - HCBU - Preslab Passed
09/14/2023 COT - HCPL - Plumbing Progress Passed
09/25/2023 COT - HCEL - Electrical Intermediate Passed
09/25/2023 COT - HCBU - Framing Passed
09/29/2023 COT - HCBU - Building Progress Passed
12/21/2023 COT - HCPL - Plumbing Above Ceiling Passed
12/21/2023 COT - HCPL - Plumbing Intermediate Passed
12/27/2023 COT - HCME - Mechanical Progress Passed 12/27/23: Mechanical and electrical above ceiling has been strapped up to prevent it touching grid ceiling. Okay to install ceiling tiles throughout building.
12/27/2023 COT - HCEL - Electrical Progress Passed 12/27/23: Mechanical and electrical above ceiling has been strapped up to prevent it touching grid ceiling. Okay to install ceiling tiles throughout building.
12/27/2023 COT - HCBU - Building Above Ceiling Passed 12/27/23: Mechanical and electrical above ceiling has been strapped up to prevent it touching grid ceiling. Okay to install ceiling tiles throughout building.
01/08/2024 ENGR Engineering Final Passed
01/08/2024 TRSP - ROW - Final/Close-Out Passed
01/31/2024 COT - HCME - Mechanical Final Passed
01/31/2024 COT - HCEL - Electrical Final Passed
01/31/2024 COT - HCPL - Plumbing Final Passed
02/29/2024 COT - FCON - Alarm - Final Passed
03/21/2024 COT - FCON - Fire - Final Passed
03/22/2024 COT - HCBU - CofO Passed
03/22/2024 COT - HCBU - Building Final Passed