Permit: TC-COM-0323-00836
Permit Details
Apply Date:
03/20/2023
Applicant:
Tim Yelaca
Description:
TI: Cardiovascular Clinic
Permit Reviews
Permit Number - TC-COM-0323-00836
Permit Status: Complete
Permit Description: TI: Cardiovascular Clinic
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/23/2023 | RESTAMP - COMMERCIAL v.1 | 05/24/2023 | APPROVED |
05/12/2023 | COMMERCIAL REVIEW - FULL v.2 | 05/23/2023 | APPROVED |
03/22/2023 | COMMERCIAL REVIEW - FULL v.1 | 04/19/2023 | REQUIRES RESUBMIT |
01/30/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/31/2024 | APPROVED |
01/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/18/2024 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0323-00836
Permite Description: TI: Cardiovascular Clinic
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
COT - HCME - Mechanical Intermediate | N/A | Requested | ||
09/14/2023 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | 9/14/23: domestic water hot & cold approved. All new pvc vents approved. |
01/05/2024 | BULD - Electrical Clearance | N/A | Not Applicable | |
01/05/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
03/12/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | Access doors, still need to be worked out, mag locks are connected to the fire alarm. |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0323-00836
Permit Description: TI: Cardiovascular Clinic
Total Completed Inspections - 20
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/28/2023 | COT - HCPL - Rough Soil | Passed | UG Plumbing, except SW corner where leak is; oK to cover elsewhere. 7/28/23: OK to cover all under slab soil pipe. |
|
08/09/2023 | COT - HCBU - Preslab | Passed | ||
09/14/2023 | COT - HCPL - Plumbing Progress | Passed | ||
09/25/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
09/25/2023 | COT - HCBU - Framing | Passed | ||
09/29/2023 | COT - HCBU - Building Progress | Passed | ||
12/21/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
12/21/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
12/27/2023 | COT - HCME - Mechanical Progress | Passed | 12/27/23: Mechanical and electrical above ceiling has been strapped up to prevent it touching grid ceiling. Okay to install ceiling tiles throughout building. | |
12/27/2023 | COT - HCEL - Electrical Progress | Passed | 12/27/23: Mechanical and electrical above ceiling has been strapped up to prevent it touching grid ceiling. Okay to install ceiling tiles throughout building. | |
12/27/2023 | COT - HCBU - Building Above Ceiling | Passed | 12/27/23: Mechanical and electrical above ceiling has been strapped up to prevent it touching grid ceiling. Okay to install ceiling tiles throughout building. | |
01/08/2024 | ENGR Engineering Final | Passed | ||
01/08/2024 | TRSP - ROW - Final/Close-Out | Passed | ||
01/31/2024 | COT - HCME - Mechanical Final | Passed | ||
01/31/2024 | COT - HCEL - Electrical Final | Passed | ||
01/31/2024 | COT - HCPL - Plumbing Final | Passed | ||
02/29/2024 | COT - FCON - Alarm - Final | Passed | ||
03/21/2024 | COT - FCON - Fire - Final | Passed | ||
03/22/2024 | COT - HCBU - CofO | Passed | ||
03/22/2024 | COT - HCBU - Building Final | Passed |