Permit: TC-COM-0323-00772
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
2350 N CAMPBELL AV
Address NEW:
2350 N CAMPBELL AV
Apply Date:
03/07/2023
Applicant:
Andrew Christopher
Description:
Shell building for Starbucks Coffee.
Permit Reviews
Permit Number - TC-COM-0323-00772
Permit Status: Complete
Permit Description: Shell building for Starbucks Coffee.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/06/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/07/2024 | APPROVED |
| 07/12/2023 | RESTAMP - COMMERCIAL v.1 | 07/24/2023 | APPROVED |
| 08/30/2023 | COMMERCIAL REVIEW - FULL v.3 | 08/31/2023 | APPROVED |
| 08/31/2023 | RESTAMP - COMMERCIAL v.1 | 09/07/2023 | APPROVED |
| 01/25/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/26/2024 | APPROVED |
| 10/18/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 10/18/2023 | APPROVED |
| 10/05/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 10/10/2023 | REQUIRES RESUBMIT |
| 07/12/2023 | COMMERCIAL REVIEW - FULL v.2 | 07/12/2023 | APPROVED |
| 08/08/2023 | COMMERCIAL REVIEW - FULL v.1 | 08/29/2023 | REQUIRES RESUBMIT |
| 03/14/2023 | COMMERCIAL REVIEW - FULL v.1 | 07/11/2023 | REQUIRES RESUBMIT |
| 08/30/2023 | COMMERCIAL REVIEW - FULL v.2 | 08/30/2023 | APPROVED |
Conditions
Permit Number - TC-COM-0323-00772
Permit Status: Complete
Permit Description: Shell building for Starbucks Coffee.
| Date | Description | Comments |
|---|---|---|
| 07/11/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 03/16/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 07/11/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 07/11/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
| 07/11/2023 | Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection. | |
| 07/11/2023 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 07/11/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 07/11/2023 | Masonry Inspection Report submittal review is required. | |
| 07/11/2023 | Pre-Manufactured Canopies Designs must be submitted and approved prior to final. | |
| 07/11/2023 | Post-Installed Anchor Inspection Report is required. | |
| 07/11/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
| 07/11/2023 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 07/11/2023 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0323-00772
Permite Description: Shell building for Starbucks Coffee.
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/03/2023 | COT - HCBU - Masonry Pregrout | N/A | Not Applicable | Not required for this project. Per Project Superintendent Tony White there is no masonry walls on this project. |
| 11/27/2023 | COT - HCBU - Building Above Ceiling | N/A | Not Applicable | Looked at drywall nailing. |
| 02/13/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0323-00772
Permit Description: Shell building for Starbucks Coffee.
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/29/2023 | COT - HCPL - Sewer | Passed | 9/29/23: sewer connection from grease interceptor to main sewer. ok to backfill. | |
| 10/05/2023 | COT - HCPL - Yard Water Line | Passed | ||
| 10/12/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 10/12/2023 | COT - HCBU - Roof Nailing | Passed | ||
| 10/31/2023 | COT - HCBU - Framing | Passed | ||
| 10/31/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
| 10/31/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 10/31/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
| 11/07/2023 | COT - HCPL - Gas Pressure Test | Passed | ||
| 11/15/2023 | COT - HCEL - Electrical Underground | Passed | ||
| 11/15/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
| 11/29/2023 | COT - HCEL - Electrical Above Ceiling | Passed | 11/29/23: conduits for secondary per plan ok to backfill. | |
| 12/11/2023 | BULD - Electrical Clearance | Passed | ||
| 12/18/2023 | COT - HCBU - Preslab | Passed | ||
| 12/18/2023 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 12/18/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 12/18/2023 | COT - HCPL - Rough Soil | Passed | ||
| 01/29/2024 | COT - HCPL - Gas Final | Passed | Gas line is complete to all gas appliances in the building and on the roof. Okay to proceed with connecting gas meter. | |
| 02/13/2024 | COT - HCME - Mechanical Final | Passed | ||
| 02/13/2024 | COT - HCPL - Plumbing Final | Passed | ||
| 02/13/2024 | COT - HCEL - Outdoor Lighting | Passed | ||
| 02/13/2024 | COT - HCEL - Electrical Final | Passed | ||
| 02/13/2024 | COT - FCON - Fire - Final | Passed | ||
| 02/16/2024 | COT - HCBU - Building Final | Passed | Shell building is complete. Okay to issue Certificate of Completion for this permit. | |
| 02/16/2024 | ENGR Engineering Final | Passed | ||
| 02/21/2024 | TRSP - ROW - Final/Close-Out | Passed | See ROW Permit. |