Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
5441 E 22ND ST BLDG 2
Apply Date:
02/10/2025
Applicant:
Ben Fyffe
Description:
Additional Application for Bldg B - refer to Master Application TC-COM-1224-02319

Permit Reviews

Permit Number - TC-COM-0225-00264
Permit Status: Complete
Permit Description: Additional Application for Bldg B - refer to Master Application TC-COM-1224-02319
Start Date Submittal Complete Date Status  
11/06/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.5 11/07/2025 APPROVED Review Details
11/03/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.4 11/04/2025 REQUIRES RESUBMIT Review Details
02/18/2025 COMMERCIAL REVIEW - FULL v.2 04/01/2025 REQUIRES RESUBMIT Review Details
11/10/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/14/2025 APPROVED Review Details
10/28/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.3 10/28/2025 REQUIRES RESUBMIT Review Details
10/17/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 10/21/2025 REQUIRES RESUBMIT Review Details
04/01/2025 COMMERCIAL REVIEW - FULL v.3 04/22/2025 APPROVED Review Details
02/13/2025 COMMERCIAL REVIEW - FULL v.1 02/13/2025 REQUIRES RESUBMIT Review Details
10/22/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.2 10/22/2025 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - TC-COM-0225-00264
Permit Status: Complete
Permit Description: Additional Application for Bldg B - refer to Master Application TC-COM-1224-02319
Date Description Comments
02/12/2025 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
03/12/2025 SPECIAL INSPECTION OF COLD-FORMED STEEL LIGHT-FRAME CONSTRUCTION IS REQUIRED.
03/12/2025 SPECIAL INSPECTION FOR CONCRETE CONSTRUCTION IS REQUIRED.
02/12/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
02/12/2025 Plan review applications expire 180 days from date of submittal unless the permit has been issued. Permits expire 180 days after issuance or last approved inspection.
03/12/2025 SPECIAL INSPECTION OF FABRICATORS IS REQUIRED.
03/12/2025 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
03/12/2025 SPECIAL INSPECTION OF MASONRY CONSTRUCTION IS REQUIRED.
03/05/2025 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
02/13/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
03/12/2025 SPECIAL INSPECTION OF SOILS IS REQUIRED.
02/12/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: Complete
Permit Number: TC-COM-0225-00264
Permite Description: Additional Application for Bldg B - refer to Master Application TC-COM-1224-02319
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
COT - FCON - Fire - Final N/A Not Ready Building number shall be provided, Gates access shall be provided, fire extinguishers shall be provided
10/20/2025 BULD - Electrical Clearance N/A Not Applicable

Completed Inspections

Permit Status: Complete
Permit Number: TC-COM-0225-00264
Permit Description: Additional Application for Bldg B - refer to Master Application TC-COM-1224-02319
Total Completed Inspections - 11
Date Description Inspector Results Comments
07/01/2025 COT - LCBU - Preslab Passed Building B, Ok to,place concrete in slab area.
09/16/2025 COT - LCBU - Building Final Passed
09/16/2025 COT - LCEL - Electrical Final Passed
10/17/2025 COT - FCON - Fire - Final Passed Passed by C Basaldua 10/14/2025
10/17/2025 ENGR Engineering Final Passed Site is complete in accordance with approved plans. Buildings are safe and accessible. Engineering is okay for CofO.
10/20/2025 COT - LCBU - Excavation/Rebar/Zoning Passed
10/20/2025 TRSP - ROW - Final/Close-Out Passed
10/20/2025 COT - LCBU - Framing Passed
10/20/2025 COT - LCBU - Masonry Pregrout Passed
10/20/2025 COT - LCBU - Roof Nailing Passed
10/20/2025 COT - LCBU - Stem Wall/Retaining Wall Passed