Permit: TC-COM-0225-00263
Permit Details
Apply Date:
02/10/2025
Applicant:
Dan Schmidt
Description:
Cooling Tower Replacement and upgrade of supporting equipment.
Permit Reviews
Permit Number - TC-COM-0225-00263
Permit Status: Issued
Permit Description: Cooling Tower Replacement and upgrade of supporting equipment.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/09/2025 | COMMERCIAL REVIEW - FULL v.3 | 05/09/2025 | APPROVED |
| 02/11/2025 | COMMERCIAL REVIEW - FULL v.1 | 03/12/2025 | REQUIRES RESUBMIT |
| 05/09/2025 | RESTAMP - COMMERCIAL v.1 | 05/13/2025 | APPROVED |
| 04/14/2025 | COMMERCIAL REVIEW - FULL v.2 | 05/05/2025 | REQUIRES RESUBMIT |
| 04/21/2026 | SPECIAL INSPECTION REVIEW v.1 | 04/24/2026 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0225-00263
Permit Status: Issued
Permit Description: Cooling Tower Replacement and upgrade of supporting equipment.
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 04/22/2026 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 04/22/2026 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 04/22/2026 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 04/22/2026 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0225-00263
Permit Status: Issued
Permit Description: Cooling Tower Replacement and upgrade of supporting equipment.
| Date | Description | Comments |
|---|---|---|
| 02/11/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 02/11/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0225-00263
Permite Description: Cooling Tower Replacement and upgrade of supporting equipment.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/16/2026 | COT - HCME - Mechanical Progress | N/A | Partial Pass | |
| 04/20/2026 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 4/20/2026 Cooling Tower #3, Disconnect fuse inspection, energize of tower from VFD 3rd floor |