Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0224-00388
Permit Details
Apply Date:
02/29/2024
Applicant:
Rip Nicholson
Description:
ENCANTADA LA ESTANCIA PV SYSTEM* WILL CONSIST OF 69 SILFAB 500W MODULES WITH (4) GRID-TIED INVERTERS. ALL MODULES WILL BE MOUNTED ON A NEW CUSTOM STEEL PARKING CANOPY. *Structural portion only. Electrical design will be submitted as a revision.
Permit Reviews
Permit Number - TC-COM-0224-00388
Permit Status: Issued
Permit Description: ENCANTADA LA ESTANCIA PV SYSTEM* WILL CONSIST OF 69 SILFAB 500W MODULES WITH (4) GRID-TIED INVERTERS. ALL MODULES WILL BE MOUNTED ON A NEW CUSTOM STEEL PARKING CANOPY. *Structural portion only. Electrical design will be submitted as a revision.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/18/2024 | RESTAMP - COMMERCIAL v.1 | 04/22/2024 | APPROVED |
11/20/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/21/2024 | APPROVED |
04/08/2024 | COMMERCIAL REVIEW - FULL v.2 | 04/18/2024 | APPROVED |
06/20/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/21/2024 | APPROVED |
03/01/2024 | COMMERCIAL REVIEW - FULL v.1 | 04/03/2024 | REQUIRES RESUBMIT |
Conditions
Permit Number - TC-COM-0224-00388
Permit Status: Issued
Permit Description: ENCANTADA LA ESTANCIA PV SYSTEM* WILL CONSIST OF 69 SILFAB 500W MODULES WITH (4) GRID-TIED INVERTERS. ALL MODULES WILL BE MOUNTED ON A NEW CUSTOM STEEL PARKING CANOPY. *Structural portion only. Electrical design will be submitted as a revision.
Date | Description | Comments |
---|---|---|
04/22/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
04/22/2024 | SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED. | |
04/02/2024 | SPECIAL INSPECTION FOR FABRICATORS IS REQUIRED | |
04/02/2024 | SPECIAL INSPECTION FOR COLD-FORMED STEEL FRAMING IS REQUIRED | |
04/02/2024 | SPECIAL INSPECTION FOR PLACEMENT OF ANCHOR RODS AND OTHER EMBEDMENTSSUPPORTING STRUCTURAL STEEL IS REQUIRED |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0224-00388
Permite Description: ENCANTADA LA ESTANCIA PV SYSTEM* WILL CONSIST OF 69 SILFAB 500W MODULES WITH (4) GRID-TIED INVERTERS. ALL MODULES WILL BE MOUNTED ON A NEW CUSTOM STEEL PARKING CANOPY. *Structural portion only. Electrical design will be submitted as a revision.
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/15/2024 | COT - CSOL - Outdoor Lighting Solar Project | N/A | Not Applicable |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0224-00388
Permit Description: ENCANTADA LA ESTANCIA PV SYSTEM* WILL CONSIST OF 69 SILFAB 500W MODULES WITH (4) GRID-TIED INVERTERS. ALL MODULES WILL BE MOUNTED ON A NEW CUSTOM STEEL PARKING CANOPY. *Structural portion only. Electrical design will be submitted as a revision.
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/04/2024 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
07/15/2024 | COT - CSOL - Electrical Final Solar Project | Passed | Approved solar structure - DGC Clearance to TEP is required for the solar meter * Pending approval of other departments * |
|
07/15/2024 | COT - LCBU - Building Final | Passed | Approved solar structure - DGC Clearance to TEP is required for the solar meter * Pending approval of other departments * |
|
07/15/2024 | COT - LCEL - Electrical Final | Passed | ||
07/15/2024 | ENGR Engineering Final | Passed | Solar parking structure only | |
07/15/2024 | TRSP - ROW - Final/Close-Out | Passed | no work in row | |
07/15/2024 | COT - CSOL - Electrical Progress Solar Project | Passed | ||
07/15/2024 | COT - CSOL - Electrical Underground Solar Project | Passed | ||
07/15/2024 | COT - CSOL - Grounding/Bonding Solar Project | Passed | ||
07/15/2024 | BULD - Electrical Clearance | Passed | Approved solar structure - DGC Clearance to TEP is required for the solar meter |