Status:
Inspections Complete
Type:
Commercial Building
Address:
75 W RIVER RD
Address NEW:
75 W RIVER RD
Apply Date:
02/12/2024
Applicant:
Eduardo Alvarado
Description:
Tesla, Inc. is proposing to install 12 Tesla EV Supercharging stations and associated utility equipment in the existing parking lot REV1_On Sheets C-101 and C-111, cabinets and switchgear/utility meter have swapped locations to improve access and streamline service. - Details have also been added to Sheets E-001 and E-101 to demonstrate connections between charging posts and equipment.

Permit Reviews

Permit Number - TC-COM-0224-00287
Permit Status: Inspections complete
Permit Description: Tesla, Inc. is proposing to install 12 Tesla EV Supercharging stations and associated utility equipment in the existing parking lot REV1_On Sheets C-101 and C-111, cabinets and switchgear/utility meter have swapped locations to improve access and streamline service. - Details have also been added to Sheets E-001 and E-101 to demonstrate connections between charging posts and equipment.
Start Date Submittal Complete Date Status  
09/18/2025 COMMERCIAL REVIEW - FULL v.2 09/29/2025 APPROVED Review Details
02/13/2025 COMMERCIAL REVIEW - FULL v.2 02/25/2025 REQUIRES RESUBMIT Review Details
09/18/2025 COMMERCIAL REVIEW - FULL v.1 09/18/2025 REQUIRES RESUBMIT Review Details
02/13/2024 COMMERCIAL REVIEW - FULL v.1 03/19/2024 REQUIRES RESUBMIT Review Details
02/26/2025 COMMERCIAL REVIEW - FULL v.3 03/13/2025 APPROVED Review Details
03/13/2025 RESTAMP - COMMERCIAL v.1 03/17/2025 APPROVED Review Details

Conditions

Permit Number - TC-COM-0224-00287
Permit Status: Inspections complete
Permit Description: Tesla, Inc. is proposing to install 12 Tesla EV Supercharging stations and associated utility equipment in the existing parking lot REV1_On Sheets C-101 and C-111, cabinets and switchgear/utility meter have swapped locations to improve access and streamline service. - Details have also been added to Sheets E-001 and E-101 to demonstrate connections between charging posts and equipment.
Date Description Comments
02/13/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-0224-00287
Permite Description: Tesla, Inc. is proposing to install 12 Tesla EV Supercharging stations and associated utility equipment in the existing parking lot REV1_On Sheets C-101 and C-111, cabinets and switchgear/utility meter have swapped locations to improve access and streamline service. - Details have also been added to Sheets E-001 and E-101 to demonstrate connections between charging posts and equipment.
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
07/01/2025 COT - HCEL - Electrical Underground N/A Partial Pass Partial approval for primary line from pole to approximate location of riser for transformer OK to cover
7/1/25: electrical underground per approved plans at cabinet 1, cabinet 2, cabinet 3, transformer, switchgear.

Completed Inspections

Permit Status: Inspections Complete
Permit Number: TC-COM-0224-00287
Permit Description: Tesla, Inc. is proposing to install 12 Tesla EV Supercharging stations and associated utility equipment in the existing parking lot REV1_On Sheets C-101 and C-111, cabinets and switchgear/utility meter have swapped locations to improve access and streamline service. - Details have also been added to Sheets E-001 and E-101 to demonstrate connections between charging posts and equipment.
Total Completed Inspections - 10
Date Description Inspector Results Comments
07/07/2025 COT - HCBU - Preslab Passed
08/07/2025 BULD - Electrical Clearance Passed clearance address is 75 W River Rd EV
08/07/2025 COT - HCEL - Electrical Underground Passed
09/17/2025 TRSP - ROW - Final/Close-Out Passed
09/17/2025 ENGR Engineering Final Passed
09/17/2025 COT - HCEL - Electrical Progress Passed
09/17/2025 COT - HCEL - Grounding/Bonding Passed
09/17/2025 COT - HCEL - Electrical Final Passed
09/17/2025 COT - HCBU - Building Progress Passed
10/02/2025 COT - HCBU - Building Final Passed

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
2025.09.18 - COMMERCIAL REVISION NARRATIVE_V3.PDF DOCUMENTS VIEW
CONS-2025.09.18 - REVISED SHEETS_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW