Permit: TC-COM-0224-00280
Permit Details
Apply Date:
02/09/2024
Applicant:
Joqsan Valencia
Description:
Switching out a small 100amp 3 phase panel for dry cleaning machinery... THE PANEL IS ARCHING AND SO IT NEEDS TO BE REPLACED ASAP
Permit Reviews
Permit Number - TC-COM-0224-00280
Permit Status: Complete
Permit Description: Switching out a small 100amp 3 phase panel for dry cleaning machinery... THE PANEL IS ARCHING AND SO IT NEEDS TO BE REPLACED ASAP
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/12/2024 | COMMERCIAL PDSD SIMPLE REVIEW v.1 | 02/14/2024 | APPROVED |
Conditions
Permit Number - TC-COM-0224-00280
Permit Status: Complete
Permit Description: Switching out a small 100amp 3 phase panel for dry cleaning machinery... THE PANEL IS ARCHING AND SO IT NEEDS TO BE REPLACED ASAP
Date | Description | Comments |
---|---|---|
02/14/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. |
Outstanding Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00280
Permite Description: Switching out a small 100amp 3 phase panel for dry cleaning machinery... THE PANEL IS ARCHING AND SO IT NEEDS TO BE REPLACED ASAP
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/16/2024 | COT - LCEL - Electrical Progress | N/A | Not Applicable | |
02/15/2024 | COT - BULD - SWG Clearance | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: TC-COM-0224-00280
Permit Description: Switching out a small 100amp 3 phase panel for dry cleaning machinery... THE PANEL IS ARCHING AND SO IT NEEDS TO BE REPLACED ASAP
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/16/2024 | COT - LCEL - Electrical Final | Passed | ||
02/16/2024 | COT - LCEL - Grounding/Bonding | Passed | ||
02/16/2024 | BULD - Electrical Clearance | Passed | Approved 100A 3-phase panel, INCR Clearance was called into TEP at 1:35pm |